Decision model · Iron County, Utah
Pronghorn’s Antelope data-center proposal, Iron County, Utah
Pronghorn proposes five data-center buildings at Antelope in Iron County. A conditional use permit has been approved. Recovered minutes distinguish construction water, first cooling-loop fill and operating demand. Next steps include phase compliance, water-right and state air-permit checks alongside the separate future zoning-ordinance process.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will Antelope protect lawful local water, neighboring access and tribal cultural interests?
What our analysis finds
The construction-year comparison keeps phase timing and first cooling-loop fill separate from ongoing demand. Its water burden is conditional rather than actual abstraction or lawful entitlement. The approved conditional use permit does not establish state air authorization or satisfaction of all phase conditions. Tribal and cultural concerns remain distinct from quantitative water accounting.
For community and ratepayer groups: Lawful supply, noise and access protection, and meaningful tribal engagement require their own phase-specific evidence.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Cost allocation
Conditional estimate: 19.8 acre-foot (range 10–28)
Cannot assess against a target
For: Pronghorn Development, LLC
Pronghorn faces the conditional gross water-demand burden in one analytical construction year.
- What is unknown
- Actual construction-year and first-fill water burden in acre-feet by phase.
- Why
- The 10–28 acre-foot comparison assumes phase timing and fill accounting; it is not measured use.
- What would resolve it
- Phase construction and first-fill records reconciled to actual metered abstraction.
Conditional 10–28 AF construction/fill demand; illustrative midpoint 19.8 AF. Operational 7.83 AF/year is separate. Actual procurement, rights, water delivery and compliance remain Unknown.
Unknown
Not measured · A conditional use permit and modeled water burden do not establish water entitlement or lawful withdrawals.
For: Pronghorn Development, LLC, Iron County residents (as a group), Iron County Planning Commission
The project obtains applicable rights and sufficient supply while basin effects satisfy applicable conditions.
- What is unknown
- Lawful supply under applicable rights and basin-protection conditions.
- Why
- A conditional use permit and modeled water burden do not establish water entitlement or lawful withdrawals.
- What would resolve it
- Effective rights, transfers and supply terms with actual basin and withdrawal evidence.
G 1 requires pre 1945 rights in the Beryl Enterprise area. No acquired right, approved transfer, actual supply or protected aquifer condition is established; annual demand accounting cannot prove these.
Community impact
Unknown
Not measured · County land-use approval does not establish a state air order or dependable generation.
For: Pronghorn Development, LLC, Utah Division of Air Quality, Iron County residents (as a group)
The intended generation can lawfully serve the project under applicable air and building conditions.
- What is unknown
- Effective authorization and usable output for the on-site gas engines.
- Why
- County land-use approval does not establish a state air order or dependable generation.
- What would resolve it
- Issued DAQ authorization, equipment scope, compliance and accepted output records.
Described DAQ-before-building-permit condition and up-to 1.5 GWgeneration do not establish an issued order, actual emissions, IT capacity or power availability.
Unknown
Not measured · Permit approval does not establish receptor compliance or protected access during construction and operation.
For: Iron County residents (as a group), Pronghorn Development, LLC, Iron County Planning Commission
Construction and operating phases meet applicable neighborhood noise and access conditions.
- What is unknown
- Phase-specific noise and access performance against applicable conditions.
- Why
- Permit approval does not establish receptor compliance or protected access during construction and operation.
- What would resolve it
- Adopted phase conditions, access arrangements and matching measurements.
Minutes describe 65 dBboundary,55 dBresidential property and 50 dBexisting residence at night 9 pm–7 am plus phase analyses; no measurements or demonstrated compliance are available.
Unknown
Not measured · A land-use vote does not establish consultation, agreement or cultural-resource protection.
For: Indian Peaks Band of Paiutes, Pronghorn Development, LLC
Applicable cultural-resource processes and voluntary tribal participation address affected places before disturbance.
- What is unknown
- Resolution of applicable tribal and cultural concerns for the affected scope.
- Why
- A land-use vote does not establish consultation, agreement or cultural-resource protection.
- What would resolve it
- Applicable consultation and cultural-resource records with condition-specific implementation evidence.
The public record reports consultation concerns and cultural-survey conditions. It does not establish consent, completed surveys or resolved impacts. The tribal request concerns the future zoning ordinance; it does not establish a direct Antelope project consultation request or a change to the vested CUP.
Local economy
Unknown
Not measured · Proposed job totals do not establish continuing local staffing or net receipts.
For: Iron County Board of County Commissioners, Iron County residents (as a group), Pronghorn Development, LLC
Residents and local government realize supported employment and fiscal benefits after costs and separate approvals.
- What is unknown
- Lasting local employment and net public benefits by operating phase.
- Why
- Proposed job totals do not establish continuing local staffing or net receipts.
- What would resolve it
- Operating payroll and public receipts/costs with matching phase, duration and recipient definitions.
672 direct jobs conflicts with 40–50 plus contractors;68.21 bn investment,2.3 bn annual construction GRP and 55%tax reduction are attributed claims. No actual employment, fiscal result or TIF/UIPA approval is established.
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Mar 5, 2026 · happened
Planning Commission public hearing on the CUP (no action)
May 26, 2026 · happened
County adopts a 180-day pause on new data center applications
Jun 4, 2026 · decided
Planning Commission approves the Antelope Data Center CUP
Outcomes at stake:Aug 10, 2026 · happened
County Commission considers BESS clarification to Ordinance 2026-13
Oct 12, 2026 · happened
County Commission discusses Strategic Development Zone ordinance for large data centers
TODAY · Oct 20, 2026
Oct 26, 2026 · decision ahead
County Commission meeting on the Strategic Development Zone ordinance
Nov 9, 2026 · decision ahead
County Commission meeting on the Strategic Development Zone ordinance (possible action)
Nov 22, 2026 · decision ahead
Ordinance 2026-13 moratorium lapses unless repealed, extended or replaced
Date not set · decision ahead
Utah DAQ approval order for the on-site gas engines
Outcomes at stake:
Date not set · decision ahead
Reconcile each phase before mobilization
Outcomes at stake:Date not set · decision ahead
Offer consultation on the future zoning ordinance
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.