Amazon’s Lake Anna data-center campus in Louisa County, Virginia

Amazon is developing the Lake Anna data-center campus near Mineral in Louisa County, Virginia. Its cooling design calls for treated-water discharge to Sedges Creek. The county reports a January 2027 raw-water delivery commitment and AWS-funded water and sewer works serving two campuses. Final discharge conditions and delivery of the promised water service still need confirmation.

Last updated at: Oct 21, 2026

MineralVIRGINIA
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Will Lake Anna meet actual discharge conditions while receiving dependable raw-water service?

What our analysis finds

The annual discharge-volume comparison uses an owned operating profile, not observed outfall performance. The separate chlorine calculation applies a volume-weighted residual scenario to that profile. Neither establishes compliance with final permit conditions or a receiving-water effect. Raw-water delivery and AWS-funded works serving two campuses retain their separate service and project boundaries.

For community and ratepayer groups: Modeled annual discharge and an announced service commitment do not establish local water protection or dependable delivered supply.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Community impact

Conditional estimate: 1,400,000 USgal/year (range 525,000–2,625,000)

Conditional estimate: 0.04 kgTRC/year (range 0.01–0.16)

Unknown

Schedule and capacity

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Mar 19, 2026 · decided

    DEQ holds the draft permit hearing

    Outcomes at stake:
  2. May 26, 2026 · decided

    DEQ publishes comment responses

    Outcomes at stake:
  1. Date not set · decision ahead

    Compare discharge control designs

    Outcomes at stake:
  2. Date not set · decision ahead

    Sequence raw-water service

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.

Amazon’s Lake Anna data-center campus in Louisa County, Virginia | Inventurist