Decision model · Sprigg Township near Manchester, Adams County, Ohio
AWS’s proposed data-center campus, Sprigg Township, Ohio
AWS is evaluating a campus near the former Stuart plant in Sprigg Township. Voters adopted township zoning. Its application depends on the adopted text and parcel map. The moratorium, wetland permits and county incentive agreement remain separate. Requested power stages do not establish delivered capacity. Water adequacy and net local benefits remain unverified.
Last updated at: Nov 11, 2026
Stakeholders
Community and ratepayer groups
Will the Sprigg proposal protect domestic water, neighbors and existing utility customers?
What our analysis finds
Adams County certified the adoption of township zoning. The adopted text and parcel map will show which rules apply to the AWS site. The moratorium through about February 2027 and the county's incentive role remain separate. The service calculations still need matching demand, capacity and cost inputs.
For community and ratepayer groups: Domestic-service protection and noise controls need enforceable, measurable project terms rather than investment claims.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Community impact
Conditional estimate: Unknown
Cannot assess against a target
For: Adams County Regional Water District, Adams County Residents for Responsible Development (resident group)
Maintain adequate domestic service for existing customers while serving the proposed campus.
- What is unknown
- Domestic water capacity remaining under campus demand, in gallons per day at matching peak conditions.
- Why
- Campus demand and dependable water-system capacity are not verified on the same basis.
- What would resolve it
- A matched water balance, peak-demand study and enforceable domestic-service protections.
Unknown
Context, no causal effect asserted. Approximately19.7mgal/year river cooling and40000GPDmaximum domestic are separate attributed claims; annual conversion is neither hot-day peak nor firm reserve/cap.
1 more supporting estimates or conditions
Unknown
Context, no causal effect asserted. Reported conditional USACE verification, isolated-wetland application and local process records are separate scopes, not blanket campus approval or demonstrated compliance.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Unknown
Not measured
For: Adams County Residents for Responsible Development (resident group), Sprigg Township Board of Trustees
Protect neighboring residents from material campus noise under an applicable verified standard.
- What is unknown
- Operating noise at neighbors against the applicable receptor and time-period limits.
- Why
- No complete equipment model, adopted limit and matching measurement basis is established.
- What would resolve it
- Applicable conditions, full equipment scope and independent receptor measurements.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Unknown · Terms unclear
Terms unclear · The township adopted zoning. Its application to the AWS parcels, the moratorium and the county incentive agreement remain separate questions.
For: Sprigg Township voters, Adams County Residents for Responsible Development (resident group), Sprigg Township Board of Trustees, Adams County Board of Commissioners
Conduct a source-inspectable local decision process within verified public authority.
- What is unknown
- The effective zoning, moratorium and county-agreement conditions.
- Why
- The township adopted zoning. Its application to the AWS parcels, the moratorium and the county incentive agreement remain separate questions.
- What would resolve it
- Obtain the adopted resolution and parcel map, the effective date, zoning commission and appeals-board actions, and the executed county agreement.
Unknown
Context, no causal effect asserted. Reported conditional USACE verification, isolated-wetland application and local process records are separate scopes, not blanket campus approval or demonstrated compliance.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Cost allocation
Conditional estimate: Unknown
Cannot assess against a target
For: Adams County Board of Commissioners, Adams County Regional Water District, Adams County Residents for Responsible Development (resident group)
Protect existing residents and utility customers from project-attributable service/infrastructure costs.
- What is unknown
- Infrastructure and operating costs left with other customers over the recovery period.
- Why
- Incremental costs and project recoveries are missing or not matched; overlapping recovery cannot be summed.
- What would resolve it
- Executed allocation and security terms with a nonoverlapping cost-and-recovery account.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Unknown
Not measured
For: Adams County Board of Commissioners, Adams County Residents for Responsible Development (resident group)
Realize local fiscal resources net of attributable costs and incentive treatment on one matched basis.
- What is unknown
- Net county and local public receipts in dollars per fiscal year.
- Why
- Announced investment does not establish executed payments, actual collections or public costs.
- What would resolve it
- Executed fiscal terms and recipient receipts less attributable public costs.
Unknown
Context, no causal effect asserted. At least$10bnplanned investment and at least500long-term positions are claims, not taxable value, observed jobs, net benefit or completed facilities.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Schedule and capacity
Conditional estimate: Unknown
Cannot assess against a target
For: Amazon Web Services, AES Ohio (Dayton Power & Light)
Deliver dependable commissioned service for the campus at a matched stage/load basis.
- What is unknown
- Dependable campus megawatts by requested stage and delivery date.
- Why
- Requests and grid-planning stages do not establish firm deliverable supply.
- What would resolve it
- Stage-matched service agreements, network studies and accepted delivery evidence.
Unknown
Context, no causal effect asserted. PJM request table100MWNovember2028,400July2029,700October2030,1100October2031,1300March2032 describes need, not supply. Other-project solution costs are excluded.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Unknown
Not measured
For: Amazon Web Services, Buck Canyon Properties LLC
Commission a viable campus with the needed authorizations, service and facilities.
- What is unknown
- Whether the campus meets service, permit and commissioning conditions for operation.
- Why
- Site evaluation and staged requests do not establish completed delivery or integrated acceptance.
- What would resolve it
- Phase-matched approvals, accepted service interfaces and commissioning results.
Unknown
Context, no causal effect asserted. PJM request table100MWNovember2028,400July2029,700October2030,1100October2031,1300March2032 describes need, not supply. Other-project solution costs are excluded.
2 more supporting estimates or conditions
Unknown
Context, no causal effect asserted. At least$10bnplanned investment and at least500long-term positions are claims, not taxable value, observed jobs, net benefit or completed facilities.
Unknown
Context, no causal effect asserted. Reported conditional USACE verification, isolated-wetland application and local process records are separate scopes, not blanket campus approval or demonstrated compliance.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Local economy
Unknown
Not measured
For: Adams County Board of Commissioners, Amazon Web Services
Realize long-term local employment attributable to the proposed campus.
- What is unknown
- Long-term local employment in full-time-equivalent jobs by operating stage.
- Why
- Announced jobs and investment do not establish ongoing local hiring.
- What would resolve it
- Operating payroll and staffing records with duration and local-residency definitions.
Unknown
Context, no causal effect asserted. At least$10bnplanned investment and at least500long-term positions are claims, not taxable value, observed jobs, net benefit or completed facilities.
No quantitative causal action model or numerical choice effect is admitted; evidence-review and authority records do not establish attainment.
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Jan 26, 2026 · reported recorded decision/procedure
Trustees adopt a reported no-intent resolution
Outcomes at stake:Feb 23, 2026 · reported recorded decision/procedure
Township adopts a reported 12-month moratorium
Outcomes at stake:Nov 3, 2026 · decided
Sprigg voters adopt township zoning
Outcomes at stake:TODAY · Oct 17, 2026
Feb 2027 · derived month; legal expiration unverified
Reported moratorium term reaches its estimated end
Outcomes at stake:
Feb 18, 2026 · reported recorded decision/procedure
USACE verifies a conditional wetland permit, as reported
Outcomes at stake:
Feb 3, 2026 · reported recorded decision/procedure
AES presents the Stuart-area load request to PJM
Outcomes at stake:Sep 28, 2026 · happened
PUCO notice distinguishes AES review from approved AEP terms
Outcomes at stake:
Date not set · Information review; date not set
Compare service and cost records
Outcomes at stake:Date not set · announced agreement; date not set
County considers the announced development agreement
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.