Decision model · Memphis compute / Southaven generation
xAI’s Colossus 2 data center, Memphis, and Southaven power plant
xAI’s Colossus 2 compute site is in Memphis, with MZX generation in Southaven. Its temporary-to-permanent power transition crosses the state line. Usable compute capacity remains unverified. Unit deadlines, permissions and contested proceedings remain distinct. Next steps include verifying replacement supply, temporary-unit closure and compute acceptance.
Last updated at: Oct 18, 2026
Stakeholders
Developers and operators
How should xAI and MZX sequence unit retirement and compute growth against verified supply?
What our analysis finds
The retirement calculation compares two planning cycles against the retained unit deadline. The generation-budget margin is a defined reservation-and-reserve comparison, not delivered site power. Neither calculation establishes permanent-unit emissions or compute acceptance. Water, noise and contested-permit outcomes need separate evidence.
For developers and operators: The modeled retirement and reservation choices expose a planning tradeoff; actual replacement supply and acceptance still require unit- and interface-matched records.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: Dec 2026 · On track, if the assumptions hold
On track, if the assumptions hold · The dates compared are planning assumptions rather than observed retirement.
For: MZX Tech LLC, Mississippi Commission on Environmental Quality
Actual cessation date versus the matching Dec 31, 2026 obligation
- What is unknown
- Whether temporary unit 1 actually ceases operation by its retained deadline.
- Why
- The dates compared are planning assumptions rather than observed retirement.
- What would resolve it
- Unit-specific cessation records matched to the governing deadline and reporting basis.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured
For: MZX Tech LLC, Mississippi Department of Environmental Quality, Mississippi State Conference of the NAACP
Matching unit/rate/test basis versus the permit condition
- What is unknown
- Permanent-unit nitrogen-oxide emissions against the applicable unit, rate and averaging-period limits.
- Why
- The displayed permit value does not establish a matching permanent-unit emissions basis or observed compliance.
- What would resolve it
- Applicable permit limits and matching emissions modeling, tests or monitoring, with modeled and observed results distinguished.
Unknown
Context, no causal effect asserted. A legal matter may resolve for or against a party. Its status does not establish physical compliance or delivered service.
Related decisions and context
1 more related decisions
Unknown
Not measured
For: X.AI Corp., MZX Tech LLC
Actually delivered dependable supply against actual site burden and interfaces
- What is unknown
- Actual power delivered to the Colossus 2 compute site in megawatts and by date.
- Why
- Generation announcements and defined credits do not establish the site’s dependable service boundary.
- What would resolve it
- Matching utility and generation delivery records, losses and service conditions.
0 MW by Dec 23, 2026 (range -26–0)
Informs this result. Conditional generation-budget arithmetic only; no actual dependable output, campus supply, IT capacity or delivered service is inferred.
1 more supporting estimates or conditions
Unknown
Context, no causal effect asserted. A legal matter may resolve for or against a party. Its status does not establish physical compliance or delivered service.
Related decisions and context
1 more related decisions
Unknown
Not measured
For: X.AI Corp.
Integrated technical acceptance of actual compute/power interfaces
- What is unknown
- Whether compute interfaces pass the applicable acceptance tests.
- Why
- Construction and generation milestones do not establish integrated compute readiness.
- What would resolve it
- Defined interface tests, dated results and closure of material exceptions.
Related decisions and context
Unknown
Not measured
For: MZX Tech LLC, X.AI Corp.
Actual withdrawal/use at the matching scope and period versus applicable conditions
- What is unknown
- Water supply and use against the applicable site, volume and period conditions.
- Why
- No matching conditions and supply or use evidence establish future compliance; infrastructure capacity alone is insufficient.
- What would resolve it
- Applicable water conditions and matching supply and use records, or a demand estimate with a justified inspectable basis.
Related decisions and context
Unknown
Not measured
For: MZX Tech LLC, Mississippi State Conference of the NAACP
Actual source/receiver/period-specific sound against applicable criteria
- What is unknown
- Noise at relevant receptors and times against applicable conditions.
- Why
- No location- and period-matched conditions and study or measurements establish future compliance.
- What would resolve it
- Applicable noise conditions with a matching acoustic study or operating measurements.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Mar 22, 2024 · happened
Colossus 1 provides origin context
Mar 1, 2025 · decided
Plaintiffs date Colossus 2 site acquisition
Jul 1, 2025 · happened
Plaintiffs date MZX’s power-site acquisition
Outcomes at stake:Jul 22, 2025 · happened
MLGW separates general service from compute power
Outcomes at stake:Jul 29, 2025 · decided
MDEQ accepts a conditional mobile-power route
Outcomes at stake:Aug 1, 2025 · happened
Inventory dates the first temporary units
Outcomes at stake:Jan 6, 2026 · happened
xAI reports financing and combined compute growth
Jan 8, 2026 · happened
Third Southaven compute site remains context
Feb 13, 2026 · decided
Plaintiffs give Clean Air Act notice
Outcomes at stake:Mar 11, 2026 · decided
Permanent-plant construction permit is issued
Outcomes at stake:Apr 14, 2026 · decided
NAACP plaintiffs file the federal case
Outcomes at stake:Jun 9, 2026 · happened
Board records an evidentiary-hearing schedule
Outcomes at stake:Jul 30, 2026 · decided
Commission and MZX agree unit-retirement conditions
Outcomes at stake:Aug 18, 2026 · happened
First scheduled retirement date passes in the record
Outcomes at stake:Sep 23, 2026 · decided
Five certifications are withdrawn during commissioning
Outcomes at stake:Sep 23, 2026 · happened
Biweekly report records a scoped pause in removals
Outcomes at stake:TODAY · Oct 8, 2026
Oct 30, 2026 · decision ahead
Reconcile the actual power boundary
Outcomes at stake:★ Best move for xAI: Tie capacity claims to accepted interfaces
★ Best move for MZX: Reconcile a unit-by-unit transition ledger
Nov 5, 2026 · decision ahead
Prepare the contested permit record
Outcomes at stake:Nov 10, 2026 · decision ahead
Evidentiary hearing as scheduled in June
Outcomes at stake:Dec 15, 2026 · decision ahead
Sequence power replacement before year-end unit deadlines
Outcomes at stake:★ Best move for MZX: Gate transition on accepted unit evidence
★ Best move for xAI: Bound growth to accepted supply and readiness
Assumed Dec 2026 · decision ahead
Unit 1 retires within its deadline
Outcomes at stake:★ Best move for MZX: Cease unit 1 on December 16; remove its December 23 credit
Assumed Dec 2026 · decision ahead
The proposed burden fits the retained supply
Outcomes at stake:★ Best move for xAI: Defer the entire proposed reservation
Jan 31, 2027 · decision ahead
Inspect the permanent-power and compute handoff
Outcomes at stake:★ Best move for xAI: Require integrated compute acceptance evidence
★ Best move for MZX: Document dependable supply and open interfaces
Jul 14, 2027 · decision ahead
Assess temporary-unit closure at the final listed date
Outcomes at stake:★ Best move for MZX: Reconcile every temporary-unit obligation