Decision model · Memphis compute / Southaven generation

xAI’s Colossus 2 data center, Memphis, and Southaven power plant

xAI’s Colossus 2 compute site is in Memphis, with MZX generation in Southaven. Its temporary-to-permanent power transition crosses the state line. Usable compute capacity remains unverified. Unit deadlines, permissions and contested proceedings remain distinct. Next steps include verifying replacement supply, temporary-unit closure and compute acceptance.

Last updated at: Oct 18, 2026

Memphis · computeSouthaven · powerTENNESSEEMISSISSIPPI
Approximate compute and power localities · not site boundaries

Stakeholders

Developers and operators

How should xAI and MZX sequence unit retirement and compute growth against verified supply?

What our analysis finds

The retirement calculation compares two planning cycles against the retained unit deadline. The generation-budget margin is a defined reservation-and-reserve comparison, not delivered site power. Neither calculation establishes permanent-unit emissions or compute acceptance. Water, noise and contested-permit outcomes need separate evidence.

For developers and operators: The modeled retirement and reservation choices expose a planning tradeoff; actual replacement supply and acceptance still require unit- and interface-matched records.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Schedule and capacity

Conditional estimate: Dec 2026 · On track, if the assumptions hold

Community impact

Unknown

Unknown

Unknown

Unknown

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Mar 22, 2024 · happened

    Colossus 1 provides origin context

  2. Mar 1, 2025 · decided

    Plaintiffs date Colossus 2 site acquisition

  3. Jul 1, 2025 · happened

    Plaintiffs date MZX’s power-site acquisition

    Outcomes at stake:
  4. Jul 22, 2025 · happened

    MLGW separates general service from compute power

    Outcomes at stake:
  5. Jul 29, 2025 · decided

    MDEQ accepts a conditional mobile-power route

    Outcomes at stake:
  6. Aug 1, 2025 · happened

    Inventory dates the first temporary units

    Outcomes at stake:
  7. Jan 6, 2026 · happened

    xAI reports financing and combined compute growth

  8. Jan 8, 2026 · happened

    Third Southaven compute site remains context

  9. Feb 13, 2026 · decided

    Plaintiffs give Clean Air Act notice

    Outcomes at stake:
  10. Mar 11, 2026 · decided

    Permanent-plant construction permit is issued

    Outcomes at stake:
  11. Apr 14, 2026 · decided

    NAACP plaintiffs file the federal case

    Outcomes at stake:
  12. Jun 9, 2026 · happened

    Board records an evidentiary-hearing schedule

    Outcomes at stake:
  13. Jul 30, 2026 · decided

    Commission and MZX agree unit-retirement conditions

    Outcomes at stake:
  14. Aug 18, 2026 · happened

    First scheduled retirement date passes in the record

    Outcomes at stake:
  15. Sep 23, 2026 · decided

    Five certifications are withdrawn during commissioning

    Outcomes at stake:
  16. Sep 23, 2026 · happened

    Biweekly report records a scoped pause in removals

    Outcomes at stake:
  17. TODAY · Oct 8, 2026

    Oct 30, 2026 · decision ahead

    Reconcile the actual power boundary

    Outcomes at stake:

    ★ Best move for xAI: Tie capacity claims to accepted interfaces

    ★ Best move for MZX: Reconcile a unit-by-unit transition ledger

  18. Nov 5, 2026 · decision ahead

    Prepare the contested permit record

    Outcomes at stake:
  19. Nov 10, 2026 · decision ahead

    Evidentiary hearing as scheduled in June

    Outcomes at stake:
  20. Dec 15, 2026 · decision ahead

    Sequence power replacement before year-end unit deadlines

    Outcomes at stake:

    ★ Best move for MZX: Gate transition on accepted unit evidence

    ★ Best move for xAI: Bound growth to accepted supply and readiness

  21. Assumed Dec 2026 · decision ahead

    Unit 1 retires within its deadline

    Outcomes at stake:

    ★ Best move for MZX: Cease unit 1 on December 16; remove its December 23 credit

  22. Assumed Dec 2026 · decision ahead

    The proposed burden fits the retained supply

    Outcomes at stake:

    ★ Best move for xAI: Defer the entire proposed reservation

  23. Jan 31, 2027 · decision ahead

    Inspect the permanent-power and compute handoff

    Outcomes at stake:

    ★ Best move for xAI: Require integrated compute acceptance evidence

    ★ Best move for MZX: Document dependable supply and open interfaces

  24. Jul 14, 2027 · decision ahead

    Assess temporary-unit closure at the final listed date

    Outcomes at stake:

    ★ Best move for MZX: Reconcile every temporary-unit obligation

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.