Decision model · Stillwater, OK
Google’s data-center campus, Stillwater, Oklahoma
Google is building a data-center campus in Stillwater, Oklahoma. The city identifies Google as the land buyer and reports a development agreement. Plans describe up to six phases with distinct first-two-phase payment terms. The next fiscal question is when applicable payments begin and what actual receipts can support.
Last updated at: Oct 21, 2026
Stakeholders
Community and ratepayer groups
Will Google’s Stillwater campus support local services without shifting water or infrastructure costs?
What our analysis finds
The annual-receipts example applies only to the first two phases under assumed draft terms and payment commencement. It keeps franchise revenue separate from the community payment and respects the draft franchise cap. Gross receipts do not establish net public benefit. Water rights and city use figures do not establish spare treatment capacity or a campus entitlement.
For community and ratepayer groups: Actual service costs, water availability and net public benefit remain unresolved even when a conditional gross-receipt estimate is available.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Local economy
Conditional estimate: 3,639,864 USD/year (range 0–4,764,864)
Cannot assess against a target
For: City of Stillwater
Conditional year-one municipal gross receipts for the first two eligible phases.
- What is unknown
- Actual city receipts in dollars per year and their commencement date.
- Why
- The calculation assumes first-two-phase draft applicability and realization; it does not establish cash received.
- What would resolve it
- Executed matching terms, commencement evidence and city payment records, with franchise and community payments separate.
Related decisions and context
1 more related decisions
Cost allocation
Unknown
Not measured · Gross receipts do not establish service costs or infrastructure allocation.
For: City of Stillwater, Google
Municipal net fiscal impact after public service and infrastructure costs.
- What is unknown
- The campus’s net effect on local-service affordability, in dollars over a matching period.
- Why
- Gross receipts do not establish service costs or infrastructure allocation.
- What would resolve it
- Actual receipts and attributable service and infrastructure costs for the same scope and period.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured · Water rights and city average or peak use do not establish spare treatment capacity or a project entitlement.
For: City of Stillwater, Google
Campus-phase water service and public resource protection.
- What is unknown
- Deliverable water for the campus and existing users, including treatment capacity.
- Why
- Water rights and city average or peak use do not establish spare treatment capacity or a project entitlement.
- What would resolve it
- Project demand and enforceable service rights matched to source, treatment and distribution capacity.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Nov 5, 2024 · decided
Stillwater voters pass the franchise proposition
Outcomes at stake:
Date not set · decision ahead
Plan local-service spending
Outcomes at stake:Date not set · decision ahead
Align campus service and public obligations
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.