Decision model · West Memphis, Arkansas
Google and Altitude’s data-center campus, West Memphis, Arkansas
Google and Altitude are developing a data-center campus in West Memphis. The original electric-service agreement sets staged customer contributions. A proposed expansion amendment awaits disposition. Next steps include reconciling payment milestones, effective expansion terms and service acceptance; contributions do not establish usable power or posted security.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will the West Memphis campus protect existing users and deliver verifiable local benefits?
What our analysis finds
The timing stress compares future customer contributions under the original agreement. It does not establish that payments were received or that usable power was delivered. Expansion terms, posted security and existing-customer exposure require their own operative records. The original schedule therefore remains distinct from the unresolved amendment.
For community and ratepayer groups: A customer contribution is utility revenue, not automatic proof of community benefits or protected rates.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Local economy
Conditional estimate: 330 USD million (range 145–330)
Cannot assess against a target
For: Entergy Arkansas
Conditional original-agreement future cash received by2029 under the owned joint timing/payment premise.
- What is unknown
- An applicable payment target and actual Entergy receipts in dollars over the selected schedule.
- Why
- The conditional timing example does not establish paid contributions or amended obligations.
- What would resolve it
- The original operative schedule, satisfied milestones and actual utility receipts.
Related decisions and context
1 more related decisions
Schedule and capacity
Unknown
Not measured · Payments and an expansion application do not establish network completion or dependable supply.
For: Altitude Capital, LLC (Google), Google / Alphabet Inc.
Usable electricity reaches the documented West Memphis campus under valid service terms.
- What is unknown
- Accepted campus electricity in megawatts by phase and delivery date.
- Why
- Payments and an expansion application do not establish network completion or dependable supply.
- What would resolve it
- Effective service commitments, completed interfaces and accepted delivery records.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured · Payment schedules and proposed terms do not establish posted security or full matched recovery.
For: Arkansas Public Service Commission, Entergy Arkansas
Existing users avoid project-attributable unrecovered costs within the approved agreement and applicable rate treatment.
- What is unknown
- Other-customer exposure over the original and applicable expansion recovery periods.
- Why
- Payment schedules and proposed terms do not establish posted security or full matched recovery.
- What would resolve it
- Effective allocation and security terms reconciled to actual attributable costs and receipts.
Related decisions and context
1 more related decisions
Unknown
Not measured · The announced benefit program does not establish recipient access or delivered outcomes.
For: Google / Alphabet Inc., Arkansas Public Service Commission
Local users receive the announced affordability/efficiency benefits without confusing announcement with delivery.
- What is unknown
- Actual community benefits delivered to the intended local recipients and periods.
- Why
- The announced benefit program does not establish recipient access or delivered outcomes.
- What would resolve it
- Operative program terms, recipient records and observed benefits.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Dec 2025 · decided
APSC approves original ESA; rejects upfront-payment ratemaking
Outcomes at stake:Jan 29, 2026 · decided
APSC resolves Entergy rehearing/clarification on payment amortization and Cypress ITCs
Outcomes at stake:
Date not set · decision ahead
Prepare the remaining contracted payments
Outcomes at stake:Date not set · decision ahead
Reconcile receipts and expansion protection
Outcomes at stake:Date not set · decision ahead
Resolve the expansion application on its record
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.