Decision model · 4650 FM1694 near Robstown, Nueces County, TX

Hut 8’s Beacon Point AI data-center campus near Robstown, Texas

Hut 8 is building Beacon Point, an AI data-center campus near Robstown, Texas. It reports 704 MW of leased IT capacity within a separate 1 GW utility scope. The second 352 MW IT phase is due to start delivery in Q2 2028. That is a company forecast; actual service and tenant acceptance remain unverified.

Last updated at: Oct 21, 2026

Robstown areaTEXAS
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Will Beacon Point meet applicable building and local infrastructure conditions?

What our analysis finds

The second-phase calculation applies owned delay and acceptance conditions to the 352 MW IT scope. It does not replace that quantity with the separate 1 GW utility scope or the full 704 MW leased IT total. Q2 2028 remains a company delivery forecast rather than observed service. Rent, registered-building usability and local infrastructure require their own actual records.

For community and ratepayer groups: A lease announcement and registration do not establish usable infrastructure or delivered local benefits.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Schedule and capacity

Conditional estimate: 3,168 MW-IT·month (range 0–4,224)

Unknown

Local economy

Unknown

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Jul 20, 2026 · decided

    Issuer reports second IT lease

    Outcomes at stake:
  2. Sep 9, 2026 · decided

    Building project registered

    Outcomes at stake:
  3. TODAY · Oct 20, 2026

    Date not set · decision ahead

    Second-phase service acceptance under lease conditions

    Outcomes at stake:
  1. Date not set · decision ahead

    Match second-phase service prerequisites

    Outcomes at stake:
  2. Date not set · decision ahead

    Demonstrate building and local performance

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.