Decision model · 4650 FM1694 near Robstown, Nueces County, TX
Hut 8’s Beacon Point AI data-center campus near Robstown, Texas
Hut 8 is building Beacon Point, an AI data-center campus near Robstown, Texas. It reports 704 MW of leased IT capacity within a separate 1 GW utility scope. The second 352 MW IT phase is due to start delivery in Q2 2028. That is a company forecast; actual service and tenant acceptance remain unverified.
Last updated at: Oct 21, 2026
Stakeholders
Community and ratepayer groups
Will Beacon Point meet applicable building and local infrastructure conditions?
What our analysis finds
The second-phase calculation applies owned delay and acceptance conditions to the 352 MW IT scope. It does not replace that quantity with the separate 1 GW utility scope or the full 704 MW leased IT total. Q2 2028 remains a company delivery forecast rather than observed service. Rent, registered-building usability and local infrastructure require their own actual records.
For community and ratepayer groups: A lease announcement and registration do not establish usable infrastructure or delivered local benefits.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: 3,168 MW-IT·month (range 0–4,224)
Cannot assess against a target
For: Hut 8 Corp., Beacon Point DC LLC
Conditional available capacity-time for the whole reported 352 MW IT second phase during an owned relative twelve-month planning window.
- What is unknown
- An applicable target and actual second-phase service in MW-IT-month over the selected window.
- Why
- The 352 MW IT delay stress and company Q2 2028 forecast do not establish accepted delivery.
- What would resolve it
- Second-phase lease scope, acceptance and actual available-capacity records over the matching window.
Related decisions and context
1 more related decisions
Unknown
Not measured · Registration and a campus lease do not establish construction completion or accepted use.
For: Beacon Point DC LLC, Hut 8 Corp., Texas Department of Licensing and Regulation
Actual completion and usable building acceptance for the scoped second-phase service.
- What is unknown
- Usability of the specifically registered building under applicable requirements.
- Why
- Registration and a campus lease do not establish construction completion or accepted use.
- What would resolve it
- Building-specific completion, inspection and applicable acceptance records.
Related decisions and context
1 more related decisions
Local economy
Unknown
Not measured · Leased capacity and an expected service date do not establish rent commencement or paid cash.
For: Hut 8 Corp., Beacon Point DC LLC
Rent actually earned and received under the relevant phase commencement and payment terms.
- What is unknown
- Actual rent due and received under the second-phase operative lease conditions.
- Why
- Leased capacity and an expected service date do not establish rent commencement or paid cash.
- What would resolve it
- Operative rent/commencement terms, satisfied triggers and payment records.
Related decisions and context
Unknown
Not measured · The campus power and IT announcements do not establish funded or completed local works.
For: Beacon Point DC LLC, Hut 8 Corp.
Attributable local infrastructure, environmental and resource performance for the delivered building/phase.
- What is unknown
- Fulfilment of actual local infrastructure obligations for the applicable project scope.
- Why
- The campus power and IT announcements do not establish funded or completed local works.
- What would resolve it
- Effective local obligations, funding and phase-matched works acceptance.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Jul 20, 2026 · decided
Issuer reports second IT lease
Outcomes at stake:Sep 9, 2026 · decided
Building project registered
Outcomes at stake:TODAY · Oct 20, 2026
Date not set · decision ahead
Second-phase service acceptance under lease conditions
Outcomes at stake:
Date not set · decision ahead
Match second-phase service prerequisites
Outcomes at stake:Date not set · decision ahead
Demonstrate building and local performance
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.