Decision model · LEAP District, Lebanon, Boone County, IN

Meta’s LEAP District data-center campus in Lebanon, Indiana

Meta is building a data-center campus in Lebanon’s LEAP District in Indiana. It announces $10 billion of investment and a 1 GW design, rather than operating power. City payments are tied to completed phases; Meta separately promises household energy aid. Construction and utility readiness remain the next steps toward bringing the campus into service.

Last updated at: Oct 21, 2026

LebanonINDIANA
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Will Lebanon’s campus deliver actual City payments, household assistance and protected member costs?

What our analysis finds

The City-payment example depends on completed eligible phases and applicability of the selected terms. It does not establish collected City cash. Meta’s household energy-aid promise is separate from phase payments and cooperative cost allocation. Announced investment and a 1 GW design do not establish operating power or realized local jobs.

For community and ratepayer groups: City cash, household assistance and member-cost protection need distinct recipient and performance records.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Community impact

Conditional estimate: 1,500,000 USD/year (range 0–3,000,000)

Unknown

Schedule and capacity

Unknown

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Oct 22, 2025 · decided

    Board affirms Orla-related agreement execution

    Outcomes at stake:
  2. Feb 11, 2026 · decided

    Meta and Indiana announce campus groundbreaking

    Outcomes at stake:
  3. TODAY · Oct 20, 2026

    Date not set · decision ahead

    Future applicable phase/performance qualification

    Outcomes at stake:
  1. Date not set · decision ahead

    Assess applicable city phase payments

    Outcomes at stake:
  2. Date not set · decision ahead

    Clarify customer and shared power costs

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.

Meta’s LEAP District data-center campus in Lebanon, Indiana | Inventurist