Decision model · Mount Pleasant, Wisconsin

Microsoft’s Fairwater campus, Mount Pleasant, Wisconsin

Microsoft is expanding its Fairwater data-center campus in Mount Pleasant, Wisconsin. The first facility is reported operational. A second facility is under construction with an early-2028 target. Its usable capacity, firm service and acceptance remain separate from construction progress, while local noise and fiscal obligations need matching evidence.

Last updated at: Oct 18, 2026

Mount PleasantWISCONSIN
Approximate locality · not site boundaries

Stakeholders

Developers and operators

What must Microsoft verify before reporting Fairwater Phase 2 as usable AI capacity?

What our analysis finds

Microsoft’s construction target does not establish Phase 2 acceptance or usable IT capacity. Facility-specific power and cost terms remain unverified. Startup-noise experience informs the need for matching expansion evidence without proving future compliance. Planned fiscal allocations are separate from actual receipts, levy reductions and household bills.

For developers and operators: Our suggested move is to gate usable-capacity claims on integrated acceptance and a verified facility-specific service envelope.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Schedule and capacity

Reported: Early 2028 (issuer schedule; not verified delivery) · Unverified claim

Unknown

Unknown

Unknown

Community impact

Unknown

Unknown

Cost allocation

Unknown · Terms unclear

Local economy

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Mar 30, 2023 · decided

    Village approves the initial development package

  2. Apr 2023 · decided

    Local parties enter the development agreement

  3. Jun 30, 2023 · happened

    Site preparation begins

  4. Feb 27, 2024 · happened

    Steel work and the substation plan meet

  5. May 8, 2024 · decided

    Microsoft expands the announced investment

  6. Oct 2024 · decided

    Village allows specified night work

  7. Mar 2025 · decided

    We Energies seeks large-load terms

    Outcomes at stake:
  8. Sep 18, 2025 · decided

    Microsoft commits to the second facility

    Outcomes at stake:
  9. Sep 18, 2025 · happened

    The first Fairwater design couples cooling and compute

  10. Oct 2025 · decided

    Walsh plans Phase 2 mobilization

    Outcomes at stake:
  11. Nov 10, 2025 · happened

    Local fiscal planning preserves a Phase I baseline

  12. Jan 13, 2026 · decided

    Microsoft announces infrastructure-cost commitments

    Outcomes at stake:
  13. Mar 2026 · happened

    Second-facility work carries an early-2028 schedule

    Outcomes at stake:
  14. Apr 10, 2026 · happened

    DNR announces a campus air-permit hearing

  15. Apr 15, 2026 · decided

    Startup noise prompts mitigation

    Outcomes at stake:
  16. Apr 24, 2026 · decided

    PSC publishes its preliminary tariff decision

    Outcomes at stake:
  17. Jun 1, 2026 · happened

    VLC and bespoke tariff sheets take effect

    Outcomes at stake:
  18. Jun 18, 2026 · happened

    Microsoft reports mitigation results

    Outcomes at stake:
  19. Jun 23, 2026 · happened

    Microsoft announces first-facility operation

  20. Jul 2026 · happened

    Haul routes support the next site work

    Outcomes at stake:
  21. Jul 1, 2026 · happened

    Residents file a noise complaint

    Outcomes at stake:
  22. Jul 20, 2026 · happened

    Sound reduction remains under evaluation

    Outcomes at stake:
  23. Sep 28, 2026 · happened

    Village reports incentive redirection

    Outcomes at stake:
  24. TODAY · Oct 8, 2026

    Analytical window · Nov 2026 · decision ahead

    Define Phase 2 service and cost terms

    Outcomes at stake:

    ★ Best move for Microsoft: Verify the facility-specific service envelope

  25. Analytical window · Dec 2026 · decision ahead

    Carry startup lessons into expansion work

    Outcomes at stake:

    ★ Best move for Microsoft: Make cooling and local-impact acceptance explicit

  26. Analytical window · Jun 2027 · decision ahead

    Verify local obligations and fiscal performance

  27. Analytical window · Sep 2027 · decision ahead

    Join the readiness evidence

    Outcomes at stake:

    ★ Best move for Microsoft: Gate usable-capacity claims on integrated checks

  28. Analytical window · Mar 2028 · decision ahead

    Distinguish construction from usable compute

    Outcomes at stake:

    ★ Best move for Microsoft: Report only the scope evidenced ready

  29. Date not set · decision ahead

    Village Board allocates the 2027 budget

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.

Microsoft’s Fairwater campus, Mount Pleasant, Wisconsin | Inventurist