Decision model · Mount Pleasant, Wisconsin
Microsoft’s Fairwater campus, Mount Pleasant, Wisconsin
Microsoft is expanding its Fairwater data-center campus in Mount Pleasant, Wisconsin. The first facility is reported operational. A second facility is under construction with an early-2028 target. Its usable capacity, firm service and acceptance remain separate from construction progress, while local noise and fiscal obligations need matching evidence.
Last updated at: Oct 18, 2026
Stakeholders
Developers and operators
What must Microsoft verify before reporting Fairwater Phase 2 as usable AI capacity?
What our analysis finds
Microsoft’s construction target does not establish Phase 2 acceptance or usable IT capacity. Facility-specific power and cost terms remain unverified. Startup-noise experience informs the need for matching expansion evidence without proving future compliance. Planned fiscal allocations are separate from actual receipts, levy reductions and household bills.
For developers and operators: Our suggested move is to gate usable-capacity claims on integrated acceptance and a verified facility-specific service envelope.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Reported: Early 2028 (issuer schedule; not verified delivery) · Unverified claim
Unverified claim · Early 2028 is Microsoft’s schedule claim, not verified delivery or acceptance.
For: Microsoft Corporation, The Walsh Group / Walsh Construction
Phase-2 construction-completion date; not usable IT/service
- What is unknown
- The actual Phase 2 construction-completion date.
- Why
- Early 2028 is Microsoft’s schedule claim, not verified delivery or acceptance.
- What would resolve it
- Dated completion evidence for the second facility, separate from commissioning and customer acceptance.
Related decisions and context
1 more related decisions
Unknown
Not measured · No Phase 2 allocation or accepted-capacity basis is established in the reviewed record.
For: Microsoft Corporation
Phase-matched accepted critical IT MW
- What is unknown
- Usable Phase 2 IT capacity in megawatts and its availability date.
- Why
- No Phase 2 allocation or accepted-capacity basis is established in the reviewed record.
- What would resolve it
- A facility-matched capacity allocation and integrated acceptance evidence.
Related decisions and context
1 more related decisions
Unknown
Not measured · Facility service boundaries and energization records are unverified.
For: Microsoft Corporation, Wisconsin Electric Power Company (We Energies)
Firm MW and energization date for the actual Phase 2 service envelope
- What is unknown
- Firm power available to Phase 2 in megawatts and by date.
- Why
- Facility service boundaries and energization records are unverified.
- What would resolve it
- Executed service terms and phase-matched energization and dependable-supply records.
Related decisions and context
Unknown
Not measured · Applicable acceptance criteria and independent acceptance evidence are unverified.
For: Microsoft Corporation, The Walsh Group / Walsh Construction
Integrated acceptance against actual operating criteria, scope and date
- What is unknown
- Whether Phase 2 equipment and interfaces are ready to operate.
- Why
- Applicable acceptance criteria and independent acceptance evidence are unverified.
- What would resolve it
- Defined acceptance tests, open-interface closure and dated test results for the facility.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured · Site conditions and independent acoustic tests are unverified; a complaint is not a final finding.
For: Resident plaintiffs in the Fairwater noise complaint, Village of Mount Pleasant
Site/receiver/operating-mode acoustic values against applicable standards
- What is unknown
- Noise at neighboring receptors against applicable site and operating limits.
- Why
- Site conditions and independent acoustic tests are unverified; a complaint is not a final finding.
- What would resolve it
- Applicable conditions and receptor- and period-matched acoustic studies and operating measurements.
Related decisions and context
Unknown
Not measured · A Phase 2-specific allocation, target and meter series are not established.
For: Village of Mount Pleasant, Microsoft Corporation
Actual phase-matched withdrawal/use versus applicable conditions
- What is unknown
- Phase 2 water use in gallons per day or year and applicable limits.
- Why
- A Phase 2-specific allocation, target and meter series are not established.
- What would resolve it
- Facility-matched service limits, design demand and dated water-use measurements.
Related decisions and context
Cost allocation
Unknown · Terms unclear
Terms unclear · Facility terms and the full signed-order scope remain unverified.
For: Citizens Utility Board of Wisconsin, Wisconsin Electric Power Company (We Energies)
Actual allocation/recovery against applicable tariff/service terms
- What is unknown
- Project-attributable costs borne by other electric customers, in dollars over the matching period.
- Why
- Facility terms and the full signed-order scope remain unverified.
- What would resolve it
- The applicable signed order and service terms matched to project costs and recoveries.
Related decisions and context
Local economy
Unknown
Not measured
For: Village of Mount Pleasant
Actual levy change against a defensible no-project budget baseline
- What is unknown
- Actual property-levy reduction attributable to project receipts, in dollars by fiscal year.
- Why
- Allocation scenarios do not establish receipts, counterfactual spending or lower household bills.
- What would resolve it
- Actual receipts, spending and levy records with a justified comparison for the same fiscal year.
Planning allocation: $2.45m/year ($1.96m–$2.94m)
Informs this result. Budget planning allocation is $2.45 million/year (range $1.96–$2.94 million); the 75% option changes allocation arithmetic. Neither establishes actual receipts, levy reduction or lower household bills.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Mar 30, 2023 · decided
Village approves the initial development package
Apr 2023 · decided
Local parties enter the development agreement
Jun 30, 2023 · happened
Site preparation begins
Feb 27, 2024 · happened
Steel work and the substation plan meet
May 8, 2024 · decided
Microsoft expands the announced investment
Oct 2024 · decided
Village allows specified night work
Mar 2025 · decided
We Energies seeks large-load terms
Outcomes at stake:Sep 18, 2025 · decided
Microsoft commits to the second facility
Outcomes at stake:Sep 18, 2025 · happened
The first Fairwater design couples cooling and compute
Oct 2025 · decided
Walsh plans Phase 2 mobilization
Outcomes at stake:Nov 10, 2025 · happened
Local fiscal planning preserves a Phase I baseline
Jan 13, 2026 · decided
Microsoft announces infrastructure-cost commitments
Outcomes at stake:Mar 2026 · happened
Second-facility work carries an early-2028 schedule
Outcomes at stake:Apr 10, 2026 · happened
DNR announces a campus air-permit hearing
Apr 15, 2026 · decided
Startup noise prompts mitigation
Outcomes at stake:Apr 24, 2026 · decided
PSC publishes its preliminary tariff decision
Outcomes at stake:Jun 1, 2026 · happened
VLC and bespoke tariff sheets take effect
Outcomes at stake:Jun 18, 2026 · happened
Microsoft reports mitigation results
Outcomes at stake:Jun 23, 2026 · happened
Microsoft announces first-facility operation
Jul 2026 · happened
Haul routes support the next site work
Outcomes at stake:Jul 1, 2026 · happened
Residents file a noise complaint
Outcomes at stake:Jul 20, 2026 · happened
Sound reduction remains under evaluation
Outcomes at stake:Sep 28, 2026 · happened
Village reports incentive redirection
Outcomes at stake:TODAY · Oct 8, 2026
Analytical window · Nov 2026 · decision ahead
Define Phase 2 service and cost terms
Outcomes at stake:★ Best move for Microsoft: Verify the facility-specific service envelope
Analytical window · Dec 2026 · decision ahead
Carry startup lessons into expansion work
Outcomes at stake:★ Best move for Microsoft: Make cooling and local-impact acceptance explicit
Analytical window · Jun 2027 · decision ahead
Verify local obligations and fiscal performance
Analytical window · Sep 2027 · decision ahead
Join the readiness evidence
Outcomes at stake:★ Best move for Microsoft: Gate usable-capacity claims on integrated checks
Analytical window · Mar 2028 · decision ahead
Distinguish construction from usable compute
Outcomes at stake:★ Best move for Microsoft: Report only the scope evidenced ready
Date not set · decision ahead
Village Board allocates the 2027 budget
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.