Decision model · Malaga, Chelan County, Washington
Microsoft’s data-center campus, Malaga, Washington
Microsoft’s planned data-center campus is in Malaga, Chelan County. Chelan PUD authorized a 288 MW, 15-year service framework and tariff provisions. The attributed infrastructure payment is $86.5 million. Next steps require verifying actual procurement, executed assurances and commissioning; the broader Malaga tax increment area has separate scope.
Last updated at: Oct 19, 2026
Stakeholders
Community and ratepayer groups
Will Malaga’s campus protect existing services and deliver verifiable net local resources?
What our analysis finds
The authorized demand and service term do not establish dependable commissioned supply. The infrastructure payment and conditional basic charge are components of a cost account, not proof that all project costs are covered. Actual procurement, posted assurances and matched recovery remain unresolved. The wider Malaga tax increment area cannot be treated as campus-only fiscal performance.
For community and ratepayer groups: An infrastructure payment does not establish net local receipts or protection of existing customers.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Community impact
Unknown
Not measured · No scoped entitlement, supplier capacity or wastewater account is established.
For: Microsoft Corporation
Campus water service meets needs for the matched campus phase and service or financial horizon. No achieved result follows automatically from supporting conditions.
- What is unknown
- Firm water and wastewater service against coincident campus peak demand.
- Why
- No scoped entitlement, supplier capacity or wastewater account is established.
- What would resolve it
- Executed entitlement and service terms with a matched peak-demand and capacity study.
Unknown: the accepted bounded record supplies no scoped firm water service, coincident peak, wastewater conditions or executed water entitlement. No water supplier or quantity is invented.
Unknown
Not measured · Upfront payment, contemplated assurance and a conditional tariff component do not establish total costs or posted recovery.
For: Public Utility District No.1 of Chelan County
Other customers protected from project costs for the matched campus phase and service or financial horizon. No achieved result follows automatically from supporting conditions.
- What is unknown
- Costs left with other users over the applicable recovery and exit period.
- Why
- Upfront payment, contemplated assurance and a conditional tariff component do not establish total costs or posted recovery.
- What would resolve it
- Selected executed terms, posted security and a matched aggregate cost-recovery account.
Unknown
Context, no causal effect asserted. B(C) = 1000 + 0.10 × max(C − 5000, 0) USD/billing period with C authorized kW, only if incorporated by the service contract. Incorporation and billing-period duration Unknown; no monthly assertion, full shutdown bill, paid receivable or net protection.
1 more supporting estimates or conditions
Unknown
Context, no causal effect asserted. PUD says 86.5 million USD paid upfront for specified infrastructure. Staff memo describes monthly shutdown minimums, termination damages and estimated-liability assurance. Execution authorization does not supply executed selected charges or posted security; one payment does not establish total cost or achieved protection.
Related decisions and context
Local economy
Unknown
Not measured · The broader tax increment area does not isolate campus receipts and public costs.
For: Port of Chelan County
Malaga area realizes net fiscal resources for the matched campus phase and service or financial horizon. No achieved result follows automatically from supporting conditions.
- What is unknown
- Net local resources attributable to this campus in dollars per fiscal year.
- Why
- The broader tax increment area does not isolate campus receipts and public costs.
- What would resolve it
- Campus-specific fiscal obligations and collections with attributable public costs.
Unknown
Context, no causal effect asserted. Port index records December 23, 2025 approval; TIA includes Microsoft and other industrial land. Signed linked final resolution unread; no campus-specific abatement rate, allocation or net fiscal result inferred.
Unknown: the TIA includes Microsoft, Alcoa and other industrial properties; unread final linked instruments and unmatched campus revenue/costs prevent a Microsoft-specific or area net-benefit calculation.
Schedule and capacity
Unknown
Not measured · The authorized 288 MW and 15-year framework do not establish actual procurement or commissioning.
For: Microsoft Corporation, Public Utility District No.1 of Chelan County
Campus receives dependable electricity for the matched campus phase and service or financial horizon. No achieved result follows automatically from supporting conditions.
- What is unknown
- Dependable campus megawatts by operating phase and date.
- Why
- The authorized 288 MW and 15-year framework do not establish actual procurement or commissioning.
- What would resolve it
- Executed service and procurement records, completed interfaces and acceptance tests.
Unknown
Context, no causal effect asserted. Maximum authorized demand 288 MW; initial 15-year August 1, 2025–July 31, 2040 term; interim 2025 surplus-power and future at-least 80% carbon-free requirement are terms/claims. June 17 source for 2026–2040 was not determined then. None is observed load, dependable supply or actual hourly mix.
Related decisions and context
Unknown
Not measured · Agreement authority does not establish procurement or integrated commissioning.
For: Microsoft Corporation
Campus becomes operational for the matched campus phase and service or financial horizon. No achieved result follows automatically from supporting conditions.
- What is unknown
- Accepted operating scope by the applicable delivery milestone.
- Why
- Agreement authority does not establish procurement or integrated commissioning.
- What would resolve it
- Phase service and permit records with commissioning acceptance.
Unknown
Context, no causal effect asserted. Maximum authorized demand 288 MW; initial 15-year August 1, 2025–July 31, 2040 term; interim 2025 surplus-power and future at-least 80% carbon-free requirement are terms/claims. June 17 source for 2026–2040 was not determined then. None is observed load, dependable supply or actual hourly mix.
1 more supporting estimates or conditions
Unknown
Context, no causal effect asserted. PUD says 86.5 million USD paid upfront for specified infrastructure. Staff memo describes monthly shutdown minimums, termination damages and estimated-liability assurance. Execution authorization does not supply executed selected charges or posted security; one payment does not establish total cost or achieved protection.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Jun 16, 2025 · decided
PUD adopts tariff provisions and authorizes agreement execution
Outcomes at stake:Dec 23, 2025 · decided
Port approves Malaga Tax Increment Area
Outcomes at stake:
Date not set · decision ahead
Campus service and cost-protection conditions
Outcomes at stake:Date not set · decision ahead
Stage a resource-matched service increment
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.