Decision model · Piedmont / Canadian County, Oklahoma
Cloverleaf’s Project Open Sky, Piedmont, Oklahoma
Cloverleaf is preparing the Open Sky data-center campus near Piedmont for an unidentified operator. An early application covered about 634 acres; the final footprint remains unresolved. Local land-use conditions and utility agreements are still pending. Next steps include settling those conditions and how construction and water-system filling would proceed.
Last updated at: Oct 18, 2026
Stakeholders
Community and ratepayer groups
Can Piedmont protect water availability, night-time quiet and public finances as Open Sky develops?
What our analysis finds
Using one filling line instead of three reduces estimated daily water use from 124,125 to 52,125 gallons. If the proposed 75,000-gallon daily comparator applies to initial filling, the one-line range is below it. Whether initial filling counts, compliance, available city supply and filling duration remain unverified. These are Inventurist scenarios, not measured project results.
For community and ratepayer groups: Water supply, night noise and actual public receipts remain unresolved; a modeled draw or revenue projection does not establish those protections.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Community impact
Conditional estimate: 124,125 gal/day (range 92,400–159,600) · Terms unclear
Terms unclear · Scenario comparison only; compliance remains unverified. If the proposed comparator applies to initial filling, the three-line range is above it. Inventurist estimated worker numbers, washing-water use and filling rates. These are assumptions, not measured project data.
For: City of Piedmont, Piedmont Municipal Authority, Cloverleaf Infrastructure
Modeled filling-day gallons/day versus a proposed 75,000 gal/day comparator, if applicable; whether initial filling counts and compliance remain unverified.
- What is unknown
- Actual commissioning-day water draw in gallons per day and the applicable cap.
- Why
- Inventurist estimated worker numbers, washing-water use and filling rates. These are assumptions, not measured project data.
- What would resolve it
- Metered commissioning profiles and the adopted project water conditions.
Related decisions and context
Unknown
Not measured
For: Piedmont Municipal Authority, City of Piedmont, Cloverleaf Infrastructure
Deliverable source/treatment/distribution volume under applicable conditions
- What is unknown
- Deliverable city water for Open Sky in gallons per day.
- Why
- Available city supply has not been established. Water-works capacity and financing do not show how much water is available for Open Sky.
- What would resolve it
- Source, treatment and distribution capacity matched to existing demand and project service terms.
Related decisions and context
Unknown
Not measured
For: City of Piedmont, Cloverleaf Infrastructure
Measured receiver/time-specific dBA against applicable criteria
- What is unknown
- Night-time sound at identified neighboring receptors, against applicable limits.
- Why
- No matching night-noise limit, receptor baseline or operating measurements is established.
- What would resolve it
- Applicable night limits and location- and period-matched baseline or operating measurements; an acoustic estimate needs an inspectable basis.
Related decisions and context
Schedule and capacity
Conditional estimate: Oct 2030 (Jan 2030–Jul 2031)
Cannot assess against a target
Expert contribution: · Commissioning and handover
For: Cloverleaf Infrastructure, Cimarron ProjectCo LLC
Construction-completion date under the modeled start/duration
- What is unknown
- The actual campus construction-completion date and an applicable project target.
- Why
- The model assumes an authorized start and work durations; it does not establish approvals or completion.
- What would resolve it
- An approved project schedule, actual progress and completion records.
Related decisions and context
Unknown
Not measured
For: Cimarron Electric Cooperative, Cloverleaf Infrastructure
Site-specific service MW/date under actual agreements
- What is unknown
- Firm site power in megawatts and its delivery date.
- Why
- Early utility discussions do not establish a final service agreement.
- What would resolve it
- Completed studies and executed service terms with project demand and delivery dates.
Related decisions and context
Unknown
Not measured
For: Cloverleaf Infrastructure, City of Piedmont
Actual decision and permitted scope/conditions
- What is unknown
- Whether project zoning is approved under the applicable conditions.
- Why
- Project approval has not been verified in the sources reviewed. A general ordinance and a postponed project draft do not establish approval.
- What would resolve it
- The final project-specific council decision and its adopted conditions.
Related decisions and context
Local economy
Unknown
Not measured
For: City of Piedmont
Actual gross cash received in the applicable fiscal period; net benefit separate
- What is unknown
- Money the city actually receives from the project during the stated period. The city’s costs must be assessed separately.
- Why
- Conditional developer gross-revenue projections do not establish actual payments or net benefit.
- What would resolve it
- Executed recipient-specific terms, commencement evidence and matching city receipt records.
9,014,000 USD/year
Informs this result. Developer projection: $9.014 million/year in 2028, conditional and gross. It is not cash received or net city benefit, and it is not linked to the modeled 2030 construction date.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Jan 21, 2025 · happened
Municipal infrastructure financing approved
Outcomes at stake:Feb 23, 2026 · decided
Council adopts general IT zoning rules
Outcomes at stake:Apr 30, 2026 · happened
Applicants file annexation petition
Outcomes at stake:May 7, 2026 · happened
Utility describes early service discussions
Outcomes at stake:Jun 1, 2026 · happened
Planning packet describes original site
Outcomes at stake:Jun 22, 2026 · happened
City reports water works still progressing
Outcomes at stake:Aug 20, 2026 · happened
Developer adds Kingfisher land options
Outcomes at stake:Aug 24, 2026 · happened
Developer presents benefits and safeguards
Outcomes at stake:Sep 17, 2026 · happened
City compares requested project exceptions
Outcomes at stake:Sep 28, 2026 · decided
Council again postpones project zoning
Outcomes at stake:TODAY · Oct 14, 2026
Reported Oct 26, 2026 · decision ahead
Set the conditions for a land-use decision
Outcomes at stake:Assumed Nov 2026 · decision ahead
Agree what electricity service could be supplied before offering firm terms.
Outcomes at stake:Assumed Dec 2026 · decision ahead
Choose a conditional construction start
Outcomes at stake:During commissioning (assumed) · decision ahead
Choose how many water lines fill the systems at once.
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.