Decision model · Piedmont / Canadian County, Oklahoma

Cloverleaf’s Project Open Sky, Piedmont, Oklahoma

Cloverleaf is preparing the Open Sky data-center campus near Piedmont for an unidentified operator. An early application covered about 634 acres; the final footprint remains unresolved. Local land-use conditions and utility agreements are still pending. Next steps include settling those conditions and how construction and water-system filling would proceed.

Last updated at: Oct 18, 2026

PiedmontOKLAHOMA
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Can Piedmont protect water availability, night-time quiet and public finances as Open Sky develops?

What our analysis finds

Using one filling line instead of three reduces estimated daily water use from 124,125 to 52,125 gallons. If the proposed 75,000-gallon daily comparator applies to initial filling, the one-line range is below it. Whether initial filling counts, compliance, available city supply and filling duration remain unverified. These are Inventurist scenarios, not measured project results.

For community and ratepayer groups: Water supply, night noise and actual public receipts remain unresolved; a modeled draw or revenue projection does not establish those protections.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Community impact

Conditional estimate: 124,125 gal/day (range 92,400–159,600) · Terms unclear

Unknown

Unknown

Schedule and capacity

Conditional estimate: Oct 2030 (Jan 2030–Jul 2031)

Unknown

Unknown

Local economy

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Jan 21, 2025 · happened

    Municipal infrastructure financing approved

    Outcomes at stake:
  2. Feb 23, 2026 · decided

    Council adopts general IT zoning rules

    Outcomes at stake:
  3. Apr 30, 2026 · happened

    Applicants file annexation petition

    Outcomes at stake:
  4. May 7, 2026 · happened

    Utility describes early service discussions

    Outcomes at stake:
  5. Jun 1, 2026 · happened

    Planning packet describes original site

    Outcomes at stake:
  6. Jun 22, 2026 · happened

    City reports water works still progressing

    Outcomes at stake:
  7. Aug 20, 2026 · happened

    Developer adds Kingfisher land options

    Outcomes at stake:
  8. Aug 24, 2026 · happened

    Developer presents benefits and safeguards

    Outcomes at stake:
  9. Sep 17, 2026 · happened

    City compares requested project exceptions

    Outcomes at stake:
  10. Sep 28, 2026 · decided

    Council again postpones project zoning

    Outcomes at stake:
  11. TODAY · Oct 14, 2026

    Reported Oct 26, 2026 · decision ahead

    Set the conditions for a land-use decision

    Outcomes at stake:
  12. Assumed Nov 2026 · decision ahead

    Agree what electricity service could be supplied before offering firm terms.

    Outcomes at stake:
  13. Assumed Dec 2026 · decision ahead

    Choose a conditional construction start

    Outcomes at stake:
  14. During commissioning (assumed) · decision ahead

    Choose how many water lines fill the systems at once.

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.