Decision model · Harwood, North Dakota

Applied Digital’s Polaris Forge 2 data-center campus, Harwood, North Dakota

Applied Digital financed a 200 MW critical-IT package at Polaris Forge 2 in Harwood. Transmission and campus acceptance have separate conditions. Oracle is a named campus participant. Next steps require scope-matched service acceptance and financing evidence before the package’s usable capacity or permanent local jobs can be established.

Last updated at: Oct 20, 2026

HarwoodNORTH DAKOTA
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Will Polaris Forge 2 protect existing cooperative members and deliver lasting local jobs?

What our analysis finds

The common-delay stress reduces modeled availability for the whole financed 200 MW critical-IT package. It allocates coupon carry to the assumed no-service period while holding financed par and coupon constant. That allocation is not a new financing bill or proof of actual delay. Transmission approval, campus acceptance and permanent employment require separate evidence.

For community and ratepayer groups: Financing and modeled capacity-time do not establish permanent jobs or protection of existing cooperative members.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Schedule and capacity

Conditional estimate: 2,400 MW-IT·month (range 0–2,400)

Unknown

Cost allocation

Conditional estimate: 0 USD (range 0–72,562,500)

Unknown

Local economy

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Mar 10, 2026 · happened

    Issuer reports the ComputeCo 2 notes financing

    Outcomes at stake:
  2. Apr 15, 2026 · decided

    PSC grants temporary construction variance for Agassiz infrastructure

    Outcomes at stake:
  3. Apr 29, 2026 · decided

    NDPSC grants Agassiz transmission siting certificate and route permit

    Outcomes at stake:
  4. Jun 17, 2026 · happened

    Issuer reports the ESA financing condition satisfied

    Outcomes at stake:
  5. Jun 18, 2026 · happened

    Annual report attributes escrow release to June 18

    Outcomes at stake:
  6. Oct 1, 2026 · happened

    Minnkota files its September construction report

    Outcomes at stake:
  1. Date not set · decision ahead

    Coordinate the financed package’s acceptance

    Outcomes at stake:
  2. Date not set · decision ahead

    Time IT mobilization against service evidence

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.