Decision model · Harwood, North Dakota
Applied Digital’s Polaris Forge 2 data-center campus, Harwood, North Dakota
Applied Digital financed a 200 MW critical-IT package at Polaris Forge 2 in Harwood. Transmission and campus acceptance have separate conditions. Oracle is a named campus participant. Next steps require scope-matched service acceptance and financing evidence before the package’s usable capacity or permanent local jobs can be established.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will Polaris Forge 2 protect existing cooperative members and deliver lasting local jobs?
What our analysis finds
The common-delay stress reduces modeled availability for the whole financed 200 MW critical-IT package. It allocates coupon carry to the assumed no-service period while holding financed par and coupon constant. That allocation is not a new financing bill or proof of actual delay. Transmission approval, campus acceptance and permanent employment require separate evidence.
For community and ratepayer groups: Financing and modeled capacity-time do not establish permanent jobs or protection of existing cooperative members.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: 2,400 MW-IT·month (range 0–2,400)
Cannot assess against a target
Expert contribution: · Phased handover and acceptance
For: Oracle
Conditional availability of the whole financed 200 MW critical-IT package in an owned 12-month relative window.
- What is unknown
- An applicable target and actual whole-package service in MW-IT-month over the selected window.
- Why
- The common-delay stress assumes joint gates and does not establish delivered IT capacity.
- What would resolve it
- Full-scope acceptance and actual available-capacity records over the same window.
Related decisions and context
1 more related decisions
Unknown
Not measured · Transmission work and financing do not establish campus commissioning acceptance.
For: Applied Digital Corporation, Oracle
Actual utility and campus acceptance for the financed critical-IT scope.
- What is unknown
- Accepted usable service for the financed 200 MW critical-IT scope.
- Why
- Transmission work and financing do not establish campus commissioning acceptance.
- What would resolve it
- Scope-matched interface tests, acceptance records and exception closure.
Related decisions and context
1 more related decisions
Cost allocation
Conditional estimate: 0 USD (range 0–72,562,500)
Cannot assess against a target
For: Applied Digital Corporation
Coupon charge allocated to the same 200 MW critical-IT package’s hypothetical no-service delay. Coupon is allocated only to the labeled extra 0/3/6-month interval. Zero delay with a failed service gate means a zero-length extra allocation interval, not zero study-year interest. Total financing cost over a full-window gate failure remains Unknown.
- What is unknown
- Actual financing carry attributable to a verified no-service period, in dollars.
- Why
- The allocation assumes constant par and coupon; it is not actual cash flow, extra interest or evidence of delay.
- What would resolve it
- Operative debt terms and actual service dates reconciled to the defined allocation period.
Related decisions and context
Unknown
Not measured · Power-project approval does not establish all executed protections, security or realized recovery.
For: Cass County Electric Cooperative, Minnkota Power Cooperative
Existing cooperative members are protected from project-attributable upgrade and service costs.
- What is unknown
- Costs remaining with existing cooperative members over the recovery term.
- Why
- Power-project approval does not establish all executed protections, security or realized recovery.
- What would resolve it
- Applicable member-cost allocation and security terms with actual matched costs.
Related decisions and context
Local economy
Unknown
Not measured · Construction jobs and financed IT capacity do not establish continuing local staffing.
For: Applied Digital Corporation, Cass County Electric Cooperative
Actual permanent employment attributable to the campus, separate from construction positions.
- What is unknown
- Permanent local employment in FTE by operating phase.
- Why
- Construction jobs and financed IT capacity do not establish continuing local staffing.
- What would resolve it
- Operating payroll with construction/operation, duration and residency distinctions.
The utility’s 200–250 permanent jobs and 600–800 construction/contractor positions are separate forecasts. Campus/phase staffing boundaries and actual employment remain Unknown.
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Mar 10, 2026 · happened
Issuer reports the ComputeCo 2 notes financing
Outcomes at stake:Apr 15, 2026 · decided
PSC grants temporary construction variance for Agassiz infrastructure
Outcomes at stake:Apr 29, 2026 · decided
NDPSC grants Agassiz transmission siting certificate and route permit
Outcomes at stake:Jun 17, 2026 · happened
Issuer reports the ESA financing condition satisfied
Outcomes at stake:Jun 18, 2026 · happened
Annual report attributes escrow release to June 18
Outcomes at stake:Oct 1, 2026 · happened
Minnkota files its September construction report
Outcomes at stake:
Date not set · decision ahead
Coordinate the financed package’s acceptance
Outcomes at stake:Date not set · decision ahead
Time IT mobilization against service evidence
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.