Decision model · Chandler, Arizona
Active Infrastructure’s Price Road Innovation data-center proposal, Chandler, Arizona
Chandler City Council denied the Price Road Innovation Campus rezoning/preliminary plan and proposed development agreement 7–0 on December 11, 2025. The application combined a data center with technology-park uses. The application’s parcel exhibit labels BA Price Owner. No reapplication is established in the inspected record.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
What actual community outcomes can be attributed to the denied mixed-use Price Road proposal?
What our analysis finds
Chandler denied the rezoning, preliminary plan and proposed development agreement 7–0 on December 11, 2025. This retrospective case does not establish a reapplication. Mixed technology-park claims cannot be assigned wholly to data-center jobs or fiscal outcomes. The owner-labeled parcel exhibit and the denied draft agreement do not establish effective current obligations.
For community and ratepayer groups: The denial is fixed history; it does not quantify benefits gained or impacts avoided for residents.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Community impact
Unknown
Not measured · The denial does not establish a counterfactual preferred use or subsequent development.
For: Chandler City Council
Chandler obtains a site-appropriate land-use outcome for the rejected PLH24-0046 mixed-campus request.
- What is unknown
- The actual community land-use outcome beyond the fixed denial.
- Why
- The denial does not establish a counterfactual preferred use or subsequent development.
- What would resolve it
- Effective subsequent land-use records and an explicitly justified community comparison.
Related decisions and context
Unknown
Not measured · The owner-labeled exhibit and denied draft agreement do not establish operative current duties.
For: Active Infrastructure, BA Price Owner LLC
The identified developer and proposed counterparty resolve the specific application and parcel obligations within established authority.
- What is unknown
- Surviving parcel obligations of each actual owner or applicant.
- Why
- The owner-labeled exhibit and denied draft agreement do not establish operative current duties.
- What would resolve it
- Recorded ownership and effective surviving instruments matched to the parcel.
Related decisions and context
Unknown
Not measured · A denied proposal does not prove every physical or surrounding impact was avoided or resolved.
For: Chandler City Council
Chandler and affected residents avoid material adverse service, water, noise and other site impacts attributable to this historical proposal.
- What is unknown
- Actual site impacts and applicable protections following denial.
- Why
- A denied proposal does not prove every physical or surrounding impact was avoided or resolved.
- What would resolve it
- Site inspection, applicable condition and observed impact records.
Related decisions and context
Local economy
Unknown
Not measured · Mixed-campus projections and a denied proposal do not establish actual data-center employment.
For: Chandler City Council
Residents receive actual lasting employment benefits attributable to the specific mixed-campus proposal, distinguished from the data-center portion.
- What is unknown
- Lasting local jobs attributable specifically to the data-center component and operating period.
- Why
- Mixed-campus projections and a denied proposal do not establish actual data-center employment.
- What would resolve it
- Component-specific operating payroll and duration/local-residency evidence, if development occurs.
Related decisions and context
Unknown
Not measured · Mixed-campus fiscal claims are not realized data-center receipts less public costs.
For: Chandler City Council
Chandler realizes project-attributable public receipts net of attributable public costs for the rejected mixed-campus scope.
- What is unknown
- Actual net City resources attributable to the proposal and its disposition.
- Why
- Mixed-campus fiscal claims are not realized data-center receipts less public costs.
- What would resolve it
- City receipt and cost records with justified component attribution and period.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Aug 19, 2025 · happened
Application boundary exhibits dated and surveyor-signed
Oct 15, 2025 · happened
Planning agenda identifies the submitted application
Dec 11, 2025 · decided
Council denies Price Road Innovation rezoning/development proposal
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.