Decision model · North of Pima County Fairgrounds, unincorporated Pima County, Arizona
Beale Infrastructure’s Project Blue data-center campus, Pima County, Arizona
Beale Infrastructure proposes Project Blue on 290 acres in unincorporated Pima County. The County route followed Tucson’s decision against annexation. Land was conveyed in December 2025, while the April 2026 record still required permit corrections. Next steps require applicable occupancy, water and power conditions to be verified.
Last updated at: Oct 19, 2026
Stakeholders
Community and ratepayer groups
Will Project Blue deliver verifiable contributions and jobs while protecting neighbors and water service?
What our analysis finds
Project Blue follows the County route after Tucson declined annexation; land was conveyed in December 2025, while the April 2026 record still required permit corrections. The county-tax example depends on source-year valuation and collection assumptions for 2030. The compensation example multiplies an owned annual compensation definition by staffing. Neither establishes actual receipts or lasting jobs; donation, occupancy and service obligations must be reconciled to their operative instruments.
For community and ratepayer groups: Taxes, compensation and donations are different benefits with different recipients and triggers; none establishes water or neighborhood protection.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Local economy
Conditional estimate: 3,674,207 USD/year
Cannot assess against a target
For: Pima County
Pima County receives calendar-2030 project-related property-tax cash under the April 23 annual forecast's construction/occupancy scope and owned timely-collection fulfillment condition.
- What is unknown
- An applicable county-tax target and actual annual county receipts for the 2030 source year.
- Why
- The modeled $3,674,207 is conditional on valuation, realization and collection.
- What would resolve it
- The applicable tax basis, assessment and actual county collection record for that year.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
1 more related decisions
Conditional estimate: 5,625,000 USD/year
Cannot assess against a target
For: Beale Infrastructure, Pima County
Project workers receive annual total compensation in the owned 75-FTE full-year scenario; Beale development and County employment-summary roles ground this analytical objective without inventing a worker proxy party.
- What is unknown
- An applicable compensation target and actual full-year campus compensation in dollars.
- Why
- The $5.625 million example uses owned FTE and compensation definitions; actual staffing is unverified.
- What would resolve it
- Full-year payroll, staffing and compensation-component records with the same FTE basis.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
2 more related decisions
Unknown
Not measured · Reported contributions do not resolve the operative instrument, occupancy trigger or payment.
For: Pima County, Beale Infrastructure
Community recipients receive applicable project donations under executed terms, distinct from relocation funding and tax revenue.
- What is unknown
- Contributions legally due and actually paid by recipient and triggering event.
- Why
- Reported contributions do not resolve the operative instrument, occupancy trigger or payment.
- What would resolve it
- Executed contribution terms, trigger satisfaction and recipient receipts.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured · Land and progress records do not establish settled water obligations or dependable service.
For: Pima County, Beale Infrastructure, City of Tucson
Campus and existing users receive adequate lawful water service with controlled resource impacts.
- What is unknown
- Adequate project water and compliance with applicable water obligations by phase.
- Why
- Land and progress records do not establish settled water obligations or dependable service.
- What would resolve it
- Current water instruments, permit status, capacity and demand evidence.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
1 more related decisions
Unknown
Not measured · No matched commitment and accepted delivery record establishes dependable capacity.
For: Tucson Electric Power, Beale Infrastructure
Campus receives usable electricity on workable service terms.
- What is unknown
- Usable campus electricity in megawatts by operating phase and date.
- Why
- No matched commitment and accepted delivery record establishes dependable capacity.
- What would resolve it
- Executed TEP terms, network scope and phase acceptance results.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
Unknown
Not measured · Project claims do not establish cost allocation, security or realized recovery.
For: Tucson Electric Power, Arizona Corporation Commission, Pima County
Existing customers are protected against unsupported project infrastructure and service costs.
- What is unknown
- Costs borne by other customers over the applicable service and recovery period.
- Why
- Project claims do not establish cost allocation, security or realized recovery.
- What would resolve it
- Applicable service, allocation and security terms reconciled to actual costs.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
Unknown
Not measured · Permits and announcements do not establish measured noise or other impact performance.
For: Pima County
Neighbors are protected from material noise, traffic and construction effects.
- What is unknown
- Operating impacts against applicable neighborhood conditions and periods.
- Why
- Permits and announcements do not establish measured noise or other impact performance.
- What would resolve it
- Adopted safeguards, complete impact studies and matching operating measurements.
Unknown
Context, no causal effect asserted. Process and obligation evidence support context; they cannot establish recipient attainment.
Related decisions and context
1 more related decisions
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Dec 2025 · happened
County records full relocation funding
Dec 24, 2025 · decided
County land sale closing
Outcomes at stake:
Dec 3, 2025 · decided
ACC energy supply agreement approval
Outcomes at stake:May 2026 · decided
Tucson reportedly revokes construction-water permit
Outcomes at stake:
Date not set · decision ahead
County considers occupancy after permit requirements are satisfied
Outcomes at stake:Date not set · decision ahead
Developer considers full-year campus staffing
Outcomes at stake:Date not set · decision ahead
Stage recruitment and construction with service readiness
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.