Decision model · Effingham County, Georgia · Savannah Gateway Industrial Hub

Octans and OpenAI’s Project Camellia data-center campus, Effingham County, Georgia

Octans and OpenAI propose a $20 billion, five-phase campus in Effingham County with 400 planned permanent jobs. Voters approved homeowner tax relief and rejected the one-percent sales-tax continuation. The separate PILOT projection is conditional. Site-plan and operating-condition decisions, redacted power terms and two lawsuits remain unresolved.

Last updated at: Nov 11, 2026

Effingham CountyGEORGIA
Approximate locality · not site boundaries

Stakeholders

Community and ratepayer groups

Will Camellia deliver verifiable local benefits while protecting water, neighbors and an open process?

What our analysis finds

Voters approved homeowner tax relief and rejected the sales-tax continuation by 139 votes. The failed continuation leaves the projected electricity-related SPLOST revenue unauthorized. The county and school PILOT comparison uses a separate forecast and depends on the existing fiscal assumptions. Actual receipts, grant terms, site review and power obligations remain unresolved.

For community and ratepayer groups: Homeowner tax relief passed. The grant terms, actual household relief and recipient-specific public receipts remain unresolved. The sales-tax continuation failed.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Local economy

Conditional estimate: 400 FTE · On track, if the assumptions hold

Conditional estimate: 20,000,000,000 USD · On track, if the assumptions hold

Conditional estimate: 66,000,000 USD/year

Community impact

Unknown

Unknown

Unknown

Approvals

Unknown

Unknown

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Jul 2026 · recorded decision or procedure

    ECIDA approves an incentive package

    Outcomes at stake:
  1. Aug 2026 · recorded decision or procedure

    Large-load power contract review is reported approved

    Outcomes at stake:
  2. Aug 4, 2026 · recorded decision or procedure

    County approves the permitted-use table

    Outcomes at stake:
  3. Aug 26, 2026 · recorded decision or procedure

    Regional advisory report is released

  4. Sep 1, 2026 · happened

    DCA history records the regional finding

    Outcomes at stake:
  5. Date not set · recorded decision or procedure

    Preliminary site-plan consideration is postponed

    Outcomes at stake:
  1. Date not set · decision ahead; date qualified

    County considers the preliminary site plan

    Outcomes at stake:
  2. Date not set · decision ahead; date qualified

    County considers data-center operating conditions

    Outcomes at stake:
  1. Date not set · decision ahead; date qualified

    Court considers the zoning-process challenge

    Outcomes at stake:
  2. Date not set · decision ahead; date qualified

    Court considers the open-government challenge

    Outcomes at stake:
  1. Nov 3, 2026 · decided

    Effingham voters approve homeowner tax relief

  2. Nov 3, 2026 · decided

    Effingham voters reject the sales-tax continuation

  1. 2032 · conditional planning comparison

    Compare five phases with a deferred fifth

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.

Octans and OpenAI’s Project Camellia data-center campus, Effingham County, Georgia | Inventurist