Decision model · Van Buren Township, Michigan
Google and Panattoni’s Project Cannoli data-center campus, Van Buren Township, Michigan
Google’s planned Project Cannoli facility in Van Buren Township has up to 1 GW maximum load. Panattoni and PDC VBT have local development roles. The MPSC conditionally approved a 20-year service term with 80% minimum billing demand. Next steps require contract response, security and final site-condition evidence before accepted service is established.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will Cannoli meet local water and site conditions while protecting existing electricity customers?
What our analysis finds
The service-window stress uses the whole planned facility scope and a common delay. The separate minimum-billing comparison uses normalized demand cases rather than a dollar bill. Conditional contract approval does not establish acceptance, posted security or delivered electricity. Local water and final site conditions remain distinct from the utility agreement.
For community and ratepayer groups: Minimum billing terms do not themselves establish full protection of existing customers or fulfillment of local water and site conditions.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: 12,000 MW-facility·month (range 0–12,000)
Cannot assess against a target
For: Google
Conditional whole-scope availability at the planned up-to 1000 MW maximum facility load over an owned relative 12-month window.
- What is unknown
- An applicable target and actual facility service in MW-facility-month over the selected window.
- Why
- The up-to-1 GW scenario and common delay do not establish delivered capacity.
- What would resolve it
- Effective full-scope commitments and accepted capacity records over the same window.
Related decisions and context
1 more related decisions
Unknown
Not measured · Conditional contract approval does not establish service acceptance or completed interfaces.
For: Google, DTE Electric Company
Actual accepted electricity service under applicable contract and site conditions.
- What is unknown
- Accepted usable facility service by the applicable contractual milestone.
- Why
- Conditional contract approval does not establish service acceptance or completed interfaces.
- What would resolve it
- Effective contract response and commissioning acceptance with material exceptions closed.
Related decisions and context
1 more related decisions
Cost allocation
Conditional estimate: 0 MW-normalized (range 0–20)
Cannot assess against a target
Expert contribution: · Power-demand measurement
For: Google
Unused minimum-billed demand exposure per normalized 100 MW contract under direct 80% terms.
- What is unknown
- Actual minimum-billing exposure under the effective demand and billing-period terms.
- Why
- The finite normalized-demand examples are not actual billing demand or dollar charges.
- What would resolve it
- Effective minimum-demand provisions, metered demand and applicable billing-period records.
Related decisions and context
1 more related decisions
Unknown
Not measured · Minimum billing alone does not establish posted security or complete aggregate recovery.
For: DTE Electric Company, Michigan Public Service Commission
Protection of other customers within the order’s explicit power-supply/customer carveout and later ratemaking reservations.
- What is unknown
- Residual other-customer exposure over the applicable service and exit term.
- Why
- Minimum billing alone does not establish posted security or complete aggregate recovery.
- What would resolve it
- Operative allocation, exit and security terms reconciled to attributable costs.
Related decisions and context
Community impact
Unknown
Not measured · Utility contract approval does not establish local water-condition fulfillment.
For: Charter Township of Van Buren, PDC VBT, LLC, Google
Project operation meets applicable GLWA connection and groundwater restrictions.
- What is unknown
- Water supply and operating compliance against applicable township conditions and peak demand.
- Why
- Utility contract approval does not establish local water-condition fulfillment.
- What would resolve it
- Adopted water conditions, design and service evidence matched to campus peak use.
Related decisions and context
Approvals
Unknown
Not measured · Planning and development documents do not establish completed final clearance.
For: PDC VBT, LLC, Charter Township of Van Buren
Affected building work meets final site-plan and engineering requirements.
- What is unknown
- Fulfilment of final adopted site and engineering conditions.
- Why
- Planning and development documents do not establish completed final clearance.
- What would resolve it
- Controlling adopted conditions, final engineering approvals and closure records.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Oct 1, 2026 · decided
MPSC conditionally approves Google PSA and CCAA
Outcomes at stake:Oct 14, 2026 · decided
Planning commission approves the site plans for the 1 GW campus
Outcomes at stake:
Date not set · decision ahead
Respond to the conditional contract order
Outcomes at stake:Date not set · decision ahead
Stage equipment commitments against service and billing evidence
Outcomes at stake:Date not set · decision ahead
Address final site and engineering conditions
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.