Decision model · Big Cedar Industrial Center along 76th Avenue SW, Cedar Rapids, IA
QTS’s Big Cedar data-center campus in Cedar Rapids
QTS is building the Big Cedar data-center campus in Cedar Rapids, Iowa, on 612 acres. QTS describes a planned $10 billion investment and up to seven buildings; Alliant Energy is its announced energy partner. Layton | Weitz says it is constructing one of the buildings. The campus is still being developed, and the inspected sources do not establish an operating date or tenant identity.
Last updated at: Oct 21, 2026
Stakeholders
Community and ratepayer groups
Will Big Cedar deliver actual community-fund cash, lasting local jobs and adequately funded services?
What our analysis finds
The annual community-fund calculation depends on the number of completed eligible phases and applicability of the selected terms. It does not establish that the City received cash. Planned investment, construction and energy-partner announcements do not establish a tenant or operating date. Net fiscal value, phase employment and infrastructure funding require separate evidence.
For community and ratepayer groups: Community-fund cash, net taxes and local jobs are separate benefits with distinct recipient and performance records.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Local economy
Conditional estimate: 300,000 USD/year (range 0–600,000)
Cannot assess against a target
For: City of Cedar Rapids
Conditional annual cash for a completed eligible phase cohort under the published city payment policy.
- What is unknown
- An applicable payment target and actual annual City community-fund receipts in dollars.
- Why
- The $0–600,000 example assumes eligible completed phases and applicable terms rather than actual collection.
- What would resolve it
- The operative agreement, phase certifications and City receipts for the matching year.
Related decisions and context
1 more related decisions
Unknown
Not measured · Planned investment and community-fund payments do not establish tax collections or net City resources.
For: City of Cedar Rapids
Retained local fiscal value after rebates and attributable service/infrastructure costs.
- What is unknown
- Net City fiscal value in dollars per fiscal year after project-related costs and incentives.
- Why
- Planned investment and community-fund payments do not establish tax collections or net City resources.
- What would resolve it
- Effective fiscal terms, assessments, receipts and attributable public costs.
Related decisions and context
Schedule and capacity
Unknown
Not measured · Construction of a building and investment claims do not establish continuing local jobs.
For: City of Cedar Rapids, QTS Cedar Rapids I LLC
Qualifying sustained employment attributable to completed project phases.
- What is unknown
- Lasting local employment by eligible operating phase in FTE.
- Why
- Construction of a building and investment claims do not establish continuing local jobs.
- What would resolve it
- Phase operating payroll and staffing records with duration and residency definitions.
Related decisions and context
1 more related decisions
Unknown
Not measured · Development progress does not establish funded obligations or accepted works.
For: City of Cedar Rapids, QTS Cedar Rapids I LLC
Adequate funding for incremental public infrastructure and services attributable to the campus.
- What is unknown
- Adequate funding and delivery of applicable City service infrastructure by phase.
- Why
- Development progress does not establish funded obligations or accepted works.
- What would resolve it
- Operative funding instruments, actual costs and phase infrastructure acceptance.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Jan 28, 2025 · decided
Original development arrangement
Outcomes at stake:Dec 2, 2025 · decided
Amended and restated development arrangement
Outcomes at stake:TODAY · Oct 20, 2026
Date not set · decision ahead
Future applicable phase/performance qualification
Outcomes at stake:
Date not set · decision ahead
Apply phase-specific payment conditions
Outcomes at stake:Date not set · decision ahead
Sequence completion and local obligations
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.