Decision model · York County, SC
QTS’s Project Cobra data-center campus in York County, South Carolina
QTS is developing Project Cobra, a data-center campus in York County, South Carolina. It plans nine buildings in three phases; the county says their approvals survive its July 2026 moratorium. A filed electric-service agreement names QTS York Infrastructure I and York Electric Cooperative for one site. Later-phase coverage, energization and local benefits remain unverified.
Last updated at: Oct 21, 2026
Stakeholders
Community and ratepayer groups
Will Cobra’s vested phases protect public customers and deliver reliable water and net local benefits?
What our analysis finds
The filed electric-service agreement identifies one site and specific counterparties. It does not establish later-phase coverage, accepted energization or complete customer-cost protection. Vested land-use approvals surviving the moratorium remain separate from delivered utility service. Net fiscal resources and reliable water require their own operative and observed records.
For community and ratepayer groups: Existing approvals and a filed agreement do not establish funded public services or net local benefits.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Unknown
Not measured · Surviving land-use approvals do not establish later-phase agreement coverage or energization.
For: Quality Technology Services, QTS York Infrastructure I LLC, York Electric Cooperative Inc, York County Council
Actual electric service for defined vested project phases under the applicable instruments.
- What is unknown
- Accepted usable electricity for each actually covered vested phase and delivery date.
- Why
- Surviving land-use approvals do not establish later-phase agreement coverage or energization.
- What would resolve it
- Effective covered-site/phase commitments, network completion and accepted delivery.
Related decisions and context
1 more related decisions
Cost allocation
Unknown
Not measured · A filed one-site agreement does not establish complete executed cost allocation, security or realized recovery.
For: York Electric Cooperative Inc, QTS York Infrastructure I LLC, York County Council
Actual allocation of specified service-site infrastructure and corrective costs without unsupported transfers.
- What is unknown
- Costs left with public utility customers over the actual site-service and recovery term.
- Why
- A filed one-site agreement does not establish complete executed cost allocation, security or realized recovery.
- What would resolve it
- Operative site-specific service and funding terms with matched costs, assurances and recoveries.
Related decisions and context
1 more related decisions
Unknown
Not measured · Nine planned buildings and vested approvals do not establish collections less public costs.
For: York County Council, Quality Technology Services
Actual attributable receipts net of applicable public support and service costs for covered property/phases.
- What is unknown
- Net local public resources in dollars by recipient and fiscal year.
- Why
- Nine planned buildings and vested approvals do not establish collections less public costs.
- What would resolve it
- Operative fiscal terms, actual receipts and attributable infrastructure/service costs.
Related decisions and context
Community impact
Unknown
Not measured · Vested planning and the electric agreement do not establish water entitlement or matched capacity.
For: York County Water & Sewer, York County Council, Quality Technology Services
Actual campus phase water demand and allocation remain compatible with reliable local service and attributable costs.
- What is unknown
- Dependable water for the actual phase and coincident peak demand.
- Why
- Vested planning and the electric agreement do not establish water entitlement or matched capacity.
- What would resolve it
- Effective water terms, phase peak demand, available capacity and accepted interfaces.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Sep 18, 2023 · decided
County approves FILOT as summarized
Outcomes at stake:Jul 13, 2026 · decided
County passes nine-month moratorium
Outcomes at stake:
Date not set · decision ahead
Substantiate inspected service obligations
Outcomes at stake:Date not set · decision ahead
Match further support to local burdens
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.