Decision model · near Broadview (unincorporated), MT
Quantica’s Big Sky data-center campus, near Broadview, Montana
Quantica’s Big Sky campus near Broadview requests an initial 500 MW utility block. Larger campus and generation requests have separate scopes. The large-new-load tariff remains proposed and executed service is unverified. Next steps include tariff, agreement, permit and discovery processes before dependable supply or cost safeguards can be established.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will Big Sky protect existing customers and substantiate local water, environmental and employment outcomes?
What our analysis finds
The joint-delay comparison covers only the initial requested 500 MW utility-service block. It measures capacity-time and does not establish delivered electricity or the larger campus’s generation. Proposed tariff safeguards and issuer agreement-status reporting are distinct from executed service and posted protection. Public permit and discovery processes retain their separate scopes and unresolved timing.
For community and ratepayer groups: Requested power and proposed safeguards do not establish protected rates, local water outcomes or lasting jobs.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Community impact
Conditional estimate: 4,500 MW-utility-service·month (range 0–6,000)
Cannot assess against a target
For: Quantica Infrastructure, LLC, Big Sky Digital Infrastructure (Quantica affiliate), NorthWestern Energy (NorthWestern Corporation)
Conditional available capacity-time for one entire initial requested500MWutility block in a relative12month study window.
- What is unknown
- An applicable target and actual initial-block capacity-time in MW-utility-service-month over the selected window.
- Why
- The requested 500 MW joint-delay scenario does not establish executed or delivered service.
- What would resolve it
- Effective block-specific service commitments and accepted capacity over the same window.
Related decisions and context
1 more related decisions
Unknown
Not measured · Separate permit requests do not establish effective permissions or operating compliance.
For: Quantica Infrastructure, LLC, Montana Department of Environmental Quality, Yellowstone County Board of County Commissioners
Actual project-scoped environmental permitting and emissions effects.
- What is unknown
- Fulfillment of applicable environmental conditions for each campus and generation scope.
- Why
- Separate permit requests do not establish effective permissions or operating compliance.
- What would resolve it
- Issued scope-specific authorizations, conditions and matching operating evidence.
Related decisions and context
1 more related decisions
Unknown
Not measured · Large-load and generation requests do not establish water entitlement, peak capacity or measured effects.
For: Quantica Infrastructure, LLC, Yellowstone County Board of County Commissioners
Actual project-scoped cooling demand, supply and local water effects.
- What is unknown
- Lawful dependable water and observed local effects against applicable demand and conditions.
- Why
- Large-load and generation requests do not establish water entitlement, peak capacity or measured effects.
- What would resolve it
- Operative water terms and a matched demand, supply and impact account.
Related decisions and context
Unknown
Not measured · Historical timing premises, a stopped initiative and pending processes do not establish all current permissions.
For: Quantica Infrastructure, LLC, Montana Public Service Commission, Yellowstone County Board of County Commissioners, Yellowstone County residents backing the data center initiative (as a group)
Applicable utility, land-use and permit conditions for the scoped project.
- What is unknown
- Effective applicable local, utility and environmental permissions.
- Why
- Historical timing premises, a stopped initiative and pending processes do not establish all current permissions.
- What would resolve it
- Controlling decisions and effective agreements with condition-closure evidence.
Related decisions and context
Local economy
Unknown
Not measured · Proposed safeguards and unverified agreement execution do not establish posted protection or full recovery.
For: NorthWestern Energy (NorthWestern Corporation), Montana Public Service Commission, Ratepayer Advocates coalition (MEIC, Honor the Earth, NW Energy Coalition and others; counsel Earthjustice)
Actual incremental-cost allocation and ratepayer protection under applicable terms.
- What is unknown
- Existing-customer residual exposure over the applicable tariff and agreement recovery term.
- Why
- Proposed safeguards and unverified agreement execution do not establish posted protection or full recovery.
- What would resolve it
- Effective tariff/service and security instruments with matched costs and recoveries.
Related decisions and context
Unknown
Not measured · Campus announcements do not establish actual staffing or net public resources.
For: Quantica Infrastructure, LLC, Yellowstone County Board of County Commissioners
Observed local economic and employment benefits for a defined project phase.
- What is unknown
- Lasting local employment and net economic benefits by phase and period.
- Why
- Campus announcements do not establish actual staffing or net public resources.
- What would resolve it
- Operating payroll and recipient receipts/costs with matching phase and duration.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Mar 31, 2026 · decided
NorthWestern files proposed Large New Load rule
Jul 2026 · happened
County directs initiative court action
Jul 2026 · happened
Planning staff deny incomplete zoning submittal
Aug 2026 · happened
Court upholds initiative invalidation
Outcomes at stake:Sep 30, 2026 · happened
Initial discovery schedule issued
TODAY · Oct 20, 2026
Dec 31, 2026 · decision ahead
Historical December31 tariff-effectiveness premise
Outcomes at stake:Date not set · decision ahead
PSC tariff hearing, date unresolved
Date not set · decision ahead
Potential review of project service agreement
Outcomes at stake:Date not set · decision ahead
Generation permit process, date unresolved
Outcomes at stake:
Date not set · decision ahead
Clarify initial-block service prerequisites
Outcomes at stake:Date not set · decision ahead
Substantiate proposed cost safeguards
Outcomes at stake:Date not set · decision ahead
Clarify environmental and local scope
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.