Decision model · Milam County, Texas
SB Energy’s Stargate data-center Buildings 1 and 2, Milam County, Texas
SB Energy’s Milam filing lists Buildings 1 and 2 at 308 and 445 MW of IT capacity. Separate leases identify landlord and tenant counterparties. Each has ready-for-service and commencement conditions. Next steps require reconciling both buildings’ service records and final county obligations before accepted capacity or public benefits can be established.
Last updated at: Oct 20, 2026
Stakeholders
Community and ratepayer groups
Will the Milam campus deliver enforceable county benefits while meeting local water conditions?
What our analysis finds
The common-delay stress treats the two buildings’ combined 753 MW-IT scope as one jointly gated package. It measures capacity-time over the selected window, not observed accepted service. Separate lease counterparties and commencement conditions remain legally distinct. The draft county instrument and reported approval do not establish final benefits or payment performance.
For community and ratepayer groups: County benefits and local water conditions need operative obligations and observations independent of the service-timing calculation.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: 9,036 MW-IT·month (range 0–9,036)
Cannot assess against a target
For: Orion DC I, LLC
Conditional availability of the combined 753 MW-IT Buildings 1/2 package during an owned relative 12-month window.
- What is unknown
- An applicable service target and actual two-building capacity-time in MW-IT-month over the selected window.
- Why
- The 753 MW-IT common-delay stress assumes joint gates and does not establish delivered service.
- What would resolve it
- Building-specific ready-for-service and commencement evidence reconciled to the full package and window.
Related decisions and context
1 more related decisions
Unknown
Not measured · The combined capacity-time scenario does not establish contractual acceptance.
For: Orion DC I, LLC, Milam County DC LLC
Actual usable service accepted under the relevant lease and separately documented service conditions.
- What is unknown
- Accepted usable capacity for each leased building and its commencement date.
- Why
- The combined capacity-time scenario does not establish contractual acceptance.
- What would resolve it
- Lease-specific tests, ready-for-service notices, commencement records and closed exceptions.
Related decisions and context
1 more related decisions
Cost allocation
Unknown
Not measured · The lease and timing comparison does not establish all effective cost-allocation and security terms.
For: Milam County, SB Energy
Existing electricity users avoid costs attributed to the announced campus and supporting generation.
- What is unknown
- Project costs allocated to covered users over the operative service and recovery term.
- Why
- The lease and timing comparison does not establish all effective cost-allocation and security terms.
- What would resolve it
- Operative allocation and assurance instruments with matched costs and recoveries.
Related decisions and context
Local economy
Unknown
Not measured · A draft abatement instrument and reported approval do not establish final terms or actual performance.
For: Milam County
County receipts and public benefits actually arise under the final applicable tax agreement.
- What is unknown
- Actual county benefit in dollars and other obligations by recipient and trigger.
- Why
- A draft abatement instrument and reported approval do not establish final terms or actual performance.
- What would resolve it
- Final executed county instrument, trigger satisfaction and recipient receipts.
The draft Chapter 312 agreement, listed action and 135m USD press headline do not establish the final executed obligation, trigger fulfilment, receipts or net public benefit.
Community impact
Unknown
Not measured · IT capacity and lease timing do not establish water design, entitlement or dependable supply.
For: Milam County, SB Energy, Orion DC I, LLC
The operating campus meets applicable water needs and local supply conditions.
- What is unknown
- Firm water supply against the two-building design and peak-use conditions.
- Why
- IT capacity and lease timing do not establish water design, entitlement or dependable supply.
- What would resolve it
- Approved water design, executed entitlement and matched peak-demand and supply evidence.
The announcement says the design minimizes water use; specific cooling technology, actual demand, supply adequacy and performance are not established.
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Nov 24, 2025 · decided
County data center tax-abatement action
Outcomes at stake:Jan 9, 2026 · happened
Partnership announces the Milam campus lease
Outcomes at stake:Sep 4, 2026 · happened
Public lease exhibits identify parties and RFS conditions
Outcomes at stake:Sep 21, 2026 · happened
Amended filing records the two-building IT scope
Outcomes at stake:
Date not set · decision ahead
Coordinate the two-building RFS record
Outcomes at stake:Date not set · decision ahead
Assess contractual commencement evidence
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.