Decision model · Caldwell County, TX
Tract’s Caldwell Valley data-center park in Texas
Tract is developing Caldwell Valley Technology Park, a data-center campus in Caldwell County, Texas. It reports nearly 3,000 acres and a contracted initial 250 MW utility block due in Q1 2028, with Bluebonnet and LCRA involved in substation plans. Wider campus plans are distinct. Utility and project prerequisites remain material to delivery; actual service is unverified.
Last updated at: Oct 21, 2026
Stakeholders
Community and ratepayer groups
Will Caldwell Valley’s initial development protect public customers and supportable local water use?
What our analysis finds
The delay comparison covers only the reported contracted initial 250 MW utility block. It measures capacity-time under a common window and joint prerequisites rather than delivered electricity. Nearly 3,000 acres and wider campus plans do not expand that modeled utility scope. Local water burdens and cost protection require their own operative and performance evidence.
For community and ratepayer groups: A contracted initial block does not establish protected customer costs or supportable local water use.
Inventurist analysis of public sources; not advice.
Outcomes at stake
Where each outcome stands, and the next decision that affects it
Schedule and capacity
Conditional estimate: 2,250 MW-utility·month (range 0–3,000)
Cannot assess against a target
For: Tract, Bluebonnet Electric Cooperative, Lower Colorado River Authority
Conditional available capacity-time for one entire initial 250 MW utility block over an owned relative 12-month window.
- What is unknown
- An applicable target and actual initial-block service in MW-utility-month over the selected window.
- Why
- The reported 250 MW contract and Q1 2028 date are not accepted delivery; the common-delay model assumes joint prerequisites.
- What would resolve it
- Operative block-specific commitments, completed substation/interfaces and accepted capacity over the same window.
Related decisions and context
1 more related decisions
Cost allocation
Unknown
Not measured · A reported contract and wider campus plan do not establish complete allocation, security or recovery.
For: Bluebonnet Electric Cooperative, Lower Colorado River Authority, Caldwell County Commissioners Court, Tract
Actual allocation of initial-block infrastructure and public costs under applicable matched terms.
- What is unknown
- Costs left with public customers over the applicable utility and infrastructure recovery period.
- Why
- A reported contract and wider campus plan do not establish complete allocation, security or recovery.
- What would resolve it
- Effective allocation/funding terms reconciled to actual project costs and recoveries.
Related decisions and context
1 more related decisions
Community impact
Unknown
Not measured · Initial electricity and acreage claims do not establish water entitlement or local service adequacy.
For: Tract, Caldwell County Commissioners Court
Phase-specific local water, permit and environmental effects compatible with documented conditions.
- What is unknown
- Local water demand and burden against lawful supply, peak conditions and applicable safeguards.
- Why
- Initial electricity and acreage claims do not establish water entitlement or local service adequacy.
- What would resolve it
- Operative water rights/service terms and matched demand, supply and impact evidence.
Related decisions and context
Decision timeline
Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.
✓ decided · × not taken · ◆ Expected · ★ Best move (Based on AI analysis; not advice; not reviewed or signed.)
Feb 11, 2025 · decided
County approves development agreement
Outcomes at stake:Oct 23, 2025 · decided
County approves First Amendment
Outcomes at stake:
Date not set · decision ahead
Scope initial tenant commitments
Outcomes at stake:Date not set · decision ahead
Clarify local and service conditions
Outcomes at stake:
Use this decision model in your work.
Discuss buying this model for your selected stakeholder view.
Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.