Vantage Oregon data-center campus

Vantage proposes three data-center buildings in Oregon, Ohio. Its presentation lists 317 MW of IT capacity and a separate full-load estimate. The county reported that voters approved the 25 MW limit. Vested rights, project phases and any litigation affect applicability. Land transfer and firm service remain unresolved.

Last updated at: Nov 11, 2026

OregonOHIO
Approximate locality ยท not site boundaries

Stakeholders

Community and ratepayer groups

Which actual charter and project safeguards will protect Oregon neighbors and public customers?

What our analysis finds

Lucas County reported that Issue 25 passed. The limit's effective date and application to Vantage depend on the operative charter, vested rights, phasing and any litigation. The 317 MW IT comparison remains conditional on legal and service readiness. Actual accepted capacity remains unverified.

For community and ratepayer groups: The county reported a Yes vote on the 25 MW limit. The City's position on project applicability and enforceable local safeguards remain unresolved.

Inventurist analysis of public sources; not advice.

Outcomes at stake

Where each outcome stands, and the next decision that affects it

Schedule and capacity

Conditional estimate: 2,140 MW-ITยทmonth (range 0โ€“3,804)

Community impact

Unknown ยท Terms unclear

Cost allocation

Unknown

Decision timeline

Decisions taken and decisions ahead. Open a step to see the parties, their options and the outcomes at stake.

โœ“ decided ยท ร— not taken ยท โ—† Expected ยท โ˜… Best move (Based on AI analysis; not advice; not reviewed or signed.)

  1. Aug 25, 2025 ยท decided

    Industrial-park rezoning approved

    Outcomes at stake:
  2. Aug 2026 ยท happened

    Petition certification accepted

  3. TODAY ยท Oct 21, 2026

    Date not set ยท decision ahead

    Consider land transfer to Vantage

  1. Nov 3, 2026 ยท decided

    Oregon voters back the 25 MW charter limit

    Outcomes at stake:
  2. TODAY ยท Oct 21, 2026

    Date not set ยท decision ahead

    Scope a contingent development commitment

    Outcomes at stake:

Use this decision model in your work.

Discuss buying this model for your selected stakeholder view.

Illustrative decision model grounded in public sources. Hypothetical choices and effects are distinct from recorded events.